Can This Project Use SolarAPP+? Battery, MPU, Existing PV and Ground-Mount Rules
The fastest way to answer “Can this project use SolarAPP+?” is to separate two questions:
- Is the project type within SolarAPP+’s current technical scope?
- Does the specific jurisdiction accept SolarAPP+ for that feature at that address?
A project can satisfy the platform’s general scope and still need a different local submission path if the jurisdiction has not enabled the applicable SolarAPP+ feature.
Battery storage
SolarAPP+ supports qualifying residential PV + storage projects. Its current eligibility guidance lists a 20 kWh limit for an individual battery and up to 80 kWh aggregate ESS capacity depending on installation location, along with other configuration requirements. See SolarAPP+: What types of systems are eligible?.
Do not stop at “SolarAPP+ supports batteries.” Check the actual battery/inverter configuration against the current eligibility checklist and confirm that the jurisdiction supports the relevant PV+ST or storage feature.
SolarAPP+’s 6.15 software release also states that the ESS permit fee was updated to $30. That is a SolarAPP+ platform fee update; it does not mean the total city/county permit cost is $30, because local AHJ fees can still apply separately. See SolarAPP+ Software Releases.
Main panel upgrade (MPU)
SolarAPP+ has platform support for main panel upgrades, but local availability varies by jurisdiction. SolarAPP+’s live availability table distinguishes PV, PV+ST, storage and MPU features. See Where is SolarAPP+ available?.
Therefore, an MPU does not automatically make every project ineligible, and it also does not mean every participating jurisdiction will process the MPU inside the SolarAPP+ path.
Existing PV
SolarAPP+ currently supports certain new PV or PV+storage projects at sites with an existing PV-only system. Its existing-systems guidance states, among other conditions, that:
- the existing system’s equipment must be on the CEC current or archived equipment lists;
- the existing system must not already include storage;
- the new system must include new solar modules and an inverter; and
- modification of the existing solar system is not permitted within that workflow.
See Existing Systems in SolarAPP+.
That means “there is already solar on the house” is no longer an automatic no — but the exact existing-system facts matter.
Ground-mounted solar
Ground-mounted solar is currently outside SolarAPP+’s scope. SolarAPP+’s August 2026 eligibility guidance lists ground-mounted solar among systems that must use the jurisdiction’s traditional permitting process. See SolarAPP+ eligibility.
Homeowner / DIY installation
This changed in 2026 and needs a more precise answer than a blanket yes/no.
SolarAPP+’s 6.15 release (June 30, 2026) says homeowners can now register and create projects in SolarAPP+, but full permit submission is currently available only in DORA-eligible jurisdictions. At the same time, SolarAPP+’s general eligibility guidance still lists systems installed by homeowners as outside the ordinary SolarAPP+ scope. See SolarAPP+ Software Releases and the current eligibility guidance.
So the practical decision is:
- Colorado / DORA-eligible location: check the current DORA + SolarAPP+ homeowner submission path for the address.
- Other jurisdictions: do not assume homeowner registration means homeowner permit submission is enabled. Check the jurisdiction feature and licensing rules; the traditional AHJ permit path may still be required.
SolarAPP+’s DORA guide also makes clear that a DORA electrical permit remains a separate required milestone in covered territory, even when SolarAPP+ performs the automated plan review. See SolarAPP+ with DORA.
Quick decision table
| Project fact | SolarAPP+ implication |
|---|---|
| Residential rooftop PV | Potentially eligible; check full criteria + jurisdiction |
| PV + battery | Potentially eligible; check storage criteria + jurisdiction feature |
| MPU | Platform-supported, but jurisdiction availability varies |
| Existing PV-only system | Potentially eligible under the current existing-system conditions |
| Existing system already has storage | Not within the cited existing-PV workflow |
| Ground mount | Outside current SolarAPP+ scope |
| Homeowner-installed system | Registration/project creation is now available; full submission is currently limited to DORA-eligible jurisdictions, otherwise check local/traditional path |
| Commercial / utility-scale | Outside current SolarAPP+ scope |
What GridPermit should ask before answering “SolarAPP+ or traditional permit?”
- jurisdiction/AHJ;
- project address or at least city;
- rooftop vs ground mount;
- new PV only, PV+storage, or storage addition;
- existing PV or existing storage;
- MPU/main-breaker work;
- contractor vs homeowner installation;
- service and equipment configuration where relevant to the current eligibility checklist.
Only after those facts are known can the answer be reduced to a reliable permit path.
SolarAPP+ eligibility and local adoption can change. The sources above are the current first-party pages reviewed on September 9, 2026. Confirm the live jurisdiction feature and current eligibility checklist before submitting.