Quick findGo anywhere.

Press ↵ to search · Esc to close

SolarAPP+ Eligibility: Battery, MPU, Existing PV & Ground Mount


The fastest way to answer “Can this project use SolarAPP+?” is to separate two questions:

  1. Is the project type within SolarAPP+’s current technical scope?
  2. Does the specific jurisdiction accept SolarAPP+ for that feature at that address?

A project can satisfy the platform’s general scope and still need a different local submission path if the jurisdiction has not enabled the applicable SolarAPP+ feature.

Battery storage

SolarAPP+ supports qualifying residential PV + storage projects. Its current eligibility guidance lists a 20 kWh limit for an individual battery and up to 80 kWh aggregate ESS capacity depending on installation location, along with other configuration requirements. See SolarAPP+: What types of systems are eligible?.

Do not stop at “SolarAPP+ supports batteries.” Check the actual battery/inverter configuration against the current eligibility checklist and confirm that the jurisdiction supports the relevant PV+ST or storage feature.

SolarAPP+’s 6.15 software release also states that the ESS permit fee was updated to $30. That is a SolarAPP+ platform fee update; it does not mean the total city/county permit cost is $30, because local AHJ fees can still apply separately. See SolarAPP+ Software Releases.

Main panel upgrade (MPU)

SolarAPP+ has platform support for main panel upgrades, but local availability varies by jurisdiction. SolarAPP+’s live availability table distinguishes PV, PV+ST, storage and MPU features. See Where is SolarAPP+ available?.

Therefore, an MPU does not automatically make every project ineligible, and it also does not mean every participating jurisdiction will process the MPU inside the SolarAPP+ path.

Existing PV

SolarAPP+ currently supports certain new PV or PV+storage projects at sites with an existing PV-only system. Its existing-systems guidance states, among other conditions, that:

  • the existing system’s equipment must be on the CEC current or archived equipment lists;
  • the existing system must not already include storage;
  • the new system must include new solar modules and an inverter; and
  • modification of the existing solar system is not permitted within that workflow.

See Existing Systems in SolarAPP+.

That means “there is already solar on the house” is no longer an automatic no — but the exact existing-system facts matter.

Ground-mounted solar

Ground-mounted solar is currently outside SolarAPP+’s scope. SolarAPP+’s August 2026 eligibility guidance lists ground-mounted solar among systems that must use the jurisdiction’s traditional permitting process. See SolarAPP+ eligibility.

Homeowner / DIY installation

This changed in 2026 and needs a more precise answer than a blanket yes/no.

SolarAPP+’s 6.15 release (June 30, 2026) says homeowners can now register and create projects in SolarAPP+, but full permit submission is currently available only in DORA-eligible jurisdictions. At the same time, SolarAPP+’s general eligibility guidance still lists systems installed by homeowners as outside the ordinary SolarAPP+ scope. See SolarAPP+ Software Releases and the current eligibility guidance.

So the practical decision is:

  • Colorado / DORA-eligible location: check the current DORA + SolarAPP+ homeowner submission path for the address.
  • Other jurisdictions: do not assume homeowner registration means homeowner permit submission is enabled. Check the jurisdiction feature and licensing rules; the traditional AHJ permit path may still be required.

SolarAPP+’s DORA guide also makes clear that a DORA electrical permit remains a separate required milestone in covered territory, even when SolarAPP+ performs the automated plan review. See SolarAPP+ with DORA.

Quick decision table

Project fact SolarAPP+ implication
Residential rooftop PV Potentially eligible; check full criteria + jurisdiction
PV + battery Potentially eligible; check storage criteria + jurisdiction feature
MPU Platform-supported, but jurisdiction availability varies
Existing PV-only system Potentially eligible under the current existing-system conditions
Existing system already has storage Not within the cited existing-PV workflow
Ground mount Outside current SolarAPP+ scope
Homeowner-installed system Registration/project creation is now available; full submission is currently limited to DORA-eligible jurisdictions, otherwise check local/traditional path
Commercial / utility-scale Outside current SolarAPP+ scope

What GridPermit should ask before answering “SolarAPP+ or traditional permit?”

  • jurisdiction/AHJ;
  • project address or at least city;
  • rooftop vs ground mount;
  • new PV only, PV+storage, or storage addition;
  • existing PV or existing storage;
  • MPU/main-breaker work;
  • contractor vs homeowner installation;
  • service and equipment configuration where relevant to the current eligibility checklist.

Only after those facts are known can the answer be reduced to a reliable permit path.

California examples: automated review is local

An automated path can differ from one city to the next. Ontario uses Symbium for eligible residential rooftop solar, while Lakewood documents a SolarAPP+ path and Cypress has its own local permit requirements. Torrance runs its own automated permit path for new rooftop systems under 38.4 kW AC on existing homes. Check the city guide before treating platform eligibility as local permit eligibility.

SolarAPP+ eligibility and local adoption can change. The sources above are the current first-party pages reviewed on September 9, 2026. Confirm the live jurisdiction feature and current eligibility checklist before submitting.

Have a project-specific permit or PTO question?

Send GridPermit the jurisdiction, utility, project scope and the exact decision or correction you are trying to resolve.

Send the project facts →Do not include account numbers or other sensitive personal information. GridPermit will label anything it cannot verify rather than guess.