Permit authority
City of Beverly Hills Development ServicesSource linked
Electric utility
Southern California Edison (SCE)Source linked
Local pathway
SolarAPP+ (automated) / over-the-counter (systems under 10kW) / electronic plan reviewProject-specific eligibility conditions apply.
See your permit path

Los Angeles County · Explore related utility guides

Source healthLast verified 2026-08-068 official sources4 of 6 core facts verified
Jump to a section
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with City of Beverly Hills Development Services and SCE before making a decision.

Research coverage

Your permit path,
at a glance.

This shows what GridPermit has verified for Beverly Hills. It does not show the status of a specific project.

  1. 01Permit authorityCity of Beverly Hills Development ServicesAuthority sourced
  2. 02DocumentsChecklist includes conditional itemsConditions apply
  3. 03InspectionInspection guidance for Beverly HillsSteps sourced
  4. 04Utility & PTOSouthern California Edison (SCE)Utility path sourced

01 / Know your path

Two approvals.
One project.

Local authority

Permit & inspection

City of Beverly Hills Development Services

Local requirements
Electric utility

Interconnection & PTO

Southern California Edison (SCE)

Utility requirements

A local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.

How to read this guide

GridPermit collects California residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Battery/solar incentive program on record

California SGIP - current category and budget check required

New applications and waitlist applications for ratepayer-funded SGIP budgets closed on December 30, 2025. New AB 209 applications have a June 30, 2028 deadline. The 2026 SGIP rate table publishes $3.10/W for solar and $1.10/Wh for storage in applicable Residential Solar and Storage Equity categories. Household eligibility and live budget availability vary by category and program administrator; check the official Program Metrics tracker before relying on an incentive.

Status on file: unknown. Verify current status before relying on this.

Sources & confidence

Confidence: High (0.9)

Source(s): SGIP - Statewide Announcements / About, 2026 Self-Generation Incentive Program Handbook, SGIP Program Metrics and Incentive Step Tracker

02 / Prepare your application

What you need.

0 of 5 markedSaved only on this device; not confirmation of permit readiness.

Sources & confidence

Confidence: High (0.9)

Source(s): Solar Panels

Permit fees

The page describes multiple fee payment steps but does not state a specific dollar amount.

Not yet verified.

Rebates on record

Rebates on record

Not yet verified.

Utility and generation supplier

Utility

Southern California Edison (SCE)

SCE's own 'Incorporated Cities and Counties Served by SCE' fact sheet (updated 3/17/2025) explicitly lists 'Beverly Hills' by name among the cities in its service area.

Sources & confidence

Confidence: High (0.9)

Source(s): Incorporated Cities and Counties Served by SCE

Generation supplier

Clean Power Alliance (CPA) - 100% Green Power (default) (Community Choice Aggregator)

Confirmed via a directly-fetched California Community Choice Association (CalCCA) press release: Beverly Hills is explicitly named among the communities that transitioned to 100% Green Power as their default CPA energy option beginning October 2022. Customers may choose another CPA option or opt out at any time.

Sources & confidence

Confidence: High (0.85)

Source(s): Eight more Clean Power Alliance Communities Choose 100% Green Power as their primary energy option

Interconnection

https://www.sce.com/clean-energy-efficiency/solar-generating-your-own-power/billing-incentives/net-energy-metering

Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Confidence: Medium (0.6)

Permit authority

City of Beverly Hills Development Services

Sources & confidence

Confidence: High (0.9)

Source(s): Solar Panels

Permit page: https://www.beverlyhills.org/766/Solar-Panels

Inspection steps

  • Schedule an inspection using the online CitySmart Portal
  • Limited next-day inspections available weekdays starting 9am, first-come first-served
  • Approved plans and the issued permit must be available on-site when the inspector arrives
Sources & confidence

Confidence: High (0.85)

Source(s): Solar Panels

Eligibility constraints

  • Property types: residential
  • Max system size (AC): 10 kW
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: SolarAPP+ (automated) / over-the-counter (systems under 10kW) / electronic plan review
  • Other conditions:
    • Residential Solar PV systems under 10kW may be submitted and reviewed over the counter
    • Additional panels on an existing system, or ground-mounted installations, require contacting Development Services before applying via SolarAPP+
Sources & confidence

Confidence: High (0.85)

Source(s): Solar Panels

Official contacts

Official contacts

Confidence: High (0.85)

Need a solar installer who handles permits in Beverly Hills?

EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.

Compare quotes from solar installers →

You'll continue on EnergySage's website. GridPermit links to EnergySage as an independent third-party resource. This link is not currently tracked for compensation.

Official sources

Official sources

Frequently Asked Questions

What utility serves solar customers in Beverly Hills, California?

Southern California Edison (SCE) is the interconnection and distribution utility for Beverly Hills. The default electricity generation supplier is Clean Power Alliance (CPA) - 100% Green Power (default), a Community Choice Aggregator (CCA), separate from Southern California Edison (SCE).

What documents are required for a solar permit in Beverly Hills?

Commonly required documents include: Completed Plan Review & Permit Application (over-the-counter pathway); SolarAPP+ Approval Document (automated pathway); Contractor authorization letter (if application is not signed by the license holder); Approved plans and issued permit must be available on-site during inspection; For ballasted (unattached, flat-roof) PV systems: seismic/wind compliance documentation per SEAOC PV1-2012 and PV2-2012, sliding friction testing, structural analysis, and a recorded maintenance affidavit.

Who do I contact about solar permits in Beverly Hills?

City of Beverly Hills Development Services, phone 310-285-1000, email cdpermits@beverlyhills.org.