GridPermit collects California residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.
Permit timeline
1–3 days
The City's own SolarAPP+ page states applicants 'receive an email within 24 business hours containing the City of Davis permit number' after submitting approved plans in person; represented here as roughly 1-3 business days (24 business hours at a standard workday) for SolarAPP+-eligible projects.
Battery/solar incentive program on record
California SGIP - current category and budget check required
New applications and waitlist applications for ratepayer-funded SGIP budgets closed on December 30, 2025. New AB 209 applications have a June 30, 2028 deadline. The 2026 SGIP rate table publishes $3.10/W for solar and $1.10/Wh for storage in applicable Residential Solar and Storage Equity categories. Household eligibility and live budget availability vary by category and program administrator; check the official Program Metrics tracker before relying on an incentive.
Status on file: unknown. Verify current status before relying on this.
Permit fees
Not yet verified.
Rebates
Not yet verified.
Utility and generation supplier
Utility
Pacific Gas and Electric Company (PG&E)
Generation supplier
Valley Clean Energy (VCE) - Standard Green (default) (Community Choice Aggregator)
Confirmed directly via Valley Clean Energy's own FAQ page: 'VCE replaces PG&E as the default electricity provider in Woodland, Davis, Winters and the unincorporated areas of Yolo County.' The default product is 'Standard Green'; customers may upgrade to 'UltraGreen' (100% renewable/carbon-free) or downgrade to 'Base Green.'
Interconnection
PG&E's own Net Energy Metering (NEM) program page — a utility-wide fact already established for other PG&E-territory records in this dataset.
Required documents
- Two printed copies of SolarAPP+ approved plans (for City stamps and building permit card) (required when: always)
Inspection steps
Not yet verified.
Eligibility constraints
- Property types: residential
- Max system size (AC): Not yet verified.
- Max system size (DC): Not yet verified.
- Max thermal capacity: Not yet verified.
- Program/pathway: SolarAPP+ (residential, roof-mounted, retrofit PV)
- Other conditions:
- The city's small residential rooftop solar system permit process and checklists substantially conform to the California Solar Permitting Guidebook's recommendations for expedited permitting
Official contacts
- City of Davis Building Division, phone: 530-757-5610, email: cddweb@cityofdavis.org, official website
Need a solar installer who handles permits in Davis?
EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.
Compare quotes from solar installers →You'll continue on EnergySage's website. GridPermit has a partner relationship with EnergySage; this link is not currently tracked, and whether the partnership results in compensation to GridPermit has not yet been confirmed.
Sources
- Building, City of Davis (government). Accessed 2026-08-05.
- FAQs, Valley Clean Energy (other_official). Accessed 2026-08-05.
- Net Energy Metering (NEM) Program, Pacific Gas and Electric Company (utility). Accessed 2026-08-05.
- SGIP - Statewide Announcements / About, Self-Generation Incentive Program (statewide administrator site) (program_administrator). Accessed 2026-08-01.
- 2026 Self-Generation Incentive Program Handbook, Self-Generation Incentive Program Program Administrators (program_administrator). Accessed 2026-08-26.
- SGIP Program Metrics and Incentive Step Tracker, Self-Generation Incentive Program Program Administrators (program_administrator). Accessed 2026-08-26.
Frequently Asked Questions
What utility serves solar customers in Davis, California?
Pacific Gas and Electric Company (PG&E) is the interconnection and distribution utility for Davis. The default electricity generation supplier is Valley Clean Energy (VCE) - Standard Green (default), a Community Choice Aggregator (CCA), separate from Pacific Gas and Electric Company (PG&E).
How long does a residential solar permit take in Davis?
The City's own SolarAPP+ page states applicants 'receive an email within 24 business hours containing the City of Davis permit number' after submitting approved plans in person; represented here as roughly 1-3 business days (24 business hours at a standard workday) for SolarAPP+-eligible projects.
What documents are required for a solar permit in Davis?
Commonly required documents include: Two printed copies of SolarAPP+ approved plans (for City stamps and building permit card).
Who do I contact about solar permits in Davis?
City of Davis Building Division, phone 530-757-5610, email cddweb@cityofdavis.org.
Related California cities
Other verified cities related to Davis. See all cities on the California solar permit guide index.
- West Sacramento, Pacific Gas and Electric Company (PG&E)
- Woodland, Pacific Gas and Electric Company (PG&E)
- Albany, Pacific Gas & Electric (PG&E)
- American Canyon, Pacific Gas & Electric (PG&E)
- Antioch, Pacific Gas & Electric (PG&E)
- Arroyo Grande, Pacific Gas & Electric (PG&E)