Lompoc Solar Permit Guide
Lompoc Utilities (Electric Division, City of Lompoc) territory · Santa Barbara County
Overview
GridPermit collects California residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.
Battery/solar incentive program on record
No battery/storage incentive program is on record for this locality.
Permit fees
Not yet verified.
Rebates
Not yet verified.
Utility and generation supplier
Utility
Lompoc Utilities (Electric Division, City of Lompoc)
Generation supplier
Lompoc Utilities (Electric Division, City of Lompoc) (utility)
Lompoc is not named among Central Coast Community Energy (3CE)'s member communities on 3CE's own official site. As a municipal utility (operating since 1923, NCPA member), Lompoc does not participate in a CCA the way IOU-served cities do — the city's own municipal utility is both the distribution and generation provider.
Interconnection
https://www.cityoflompoc.com/government/departments/utilities/electric
The City of Lompoc Electric Division's own page, which hosts its full 10-step 'Solar and Self-generation Electric Facility and Energy Storage Installation Information' process, the Self-generating Electric Facility Installation and Interconnection Application, the Interconnection Agreement, and the Customer Owned Generation - Distribution Rate Schedule G-1. As a municipal utility, this replaces a statewide IOU NEM program.
Required documents
- PV Installation and Interconnection Application (submitted to City of Lompoc Electric Utility division) (required when: always)
- Signed/initialed 'Customer Owned Generation Rate Schedule G-1' (required when: always)
- SolarAPP+ approval documents (downloaded after SolarAPP+ submittal and fee payment) (required when: always)
Inspection steps
- Request an inspection through the City's 24-hour inspection request line at 805-875-8231, at least one day prior to the desired inspection date
- Have all approval paperwork and the inspection sheet on site for the inspector
Per the City's own 'SolarAPP+' page, Step 4 (Request Inspection and Interconnectivity).
Eligibility constraints
- Property types: residential
- Max system size (AC): Not yet verified.
- Max system size (DC): Not yet verified.
- Max thermal capacity: Not yet verified.
- Program/pathway: SolarAPP+, subject to Electric Division pre-approval
- Other conditions:
- Pre-approval from the Electric Division is required before using SolarAPP+ to apply for a building permit
- Approval from the Electric Division and a signed Interconnection Agreement are required before signing a contract with a contractor
Official contacts
- City of Lompoc Building & Safety Division, phone: 805-875-8220, official website
Need a solar installer who handles permits in Lompoc?
EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.
Compare quotes from solar installers →You'll continue on EnergySage's website. GridPermit has a partner relationship with EnergySage; this link is not currently tracked, and whether the partnership results in compensation to GridPermit has not yet been confirmed.
Sources
- SolarAPP+, City of Lompoc (government). Accessed 2026-08-11.
- Electric Division, City of Lompoc (utility). Accessed 2026-08-11.
Frequently Asked Questions
What utility serves solar customers in Lompoc, California?
Lompoc Utilities (Electric Division, City of Lompoc) is the interconnection and distribution utility for Lompoc. The default electricity generation supplier is Lompoc Utilities (Electric Division, City of Lompoc), a utility, separate from Lompoc Utilities (Electric Division, City of Lompoc).
What documents are required for a solar permit in Lompoc?
Commonly required documents include: PV Installation and Interconnection Application (submitted to City of Lompoc Electric Utility division); Signed/initialed 'Customer Owned Generation Rate Schedule G-1'; SolarAPP+ approval documents (downloaded after SolarAPP+ submittal and fee payment).
Who do I contact about solar permits in Lompoc?
City of Lompoc Building & Safety Division, phone 805-875-8220.
Related California cities
Other verified cities related to Lompoc. See all cities on the California solar permit guide index.
- Carpinteria, Southern California Edison (SCE)
- Goleta, Southern California Edison (SCE)
- Santa Barbara, Southern California Edison (SCE)
- Santa Maria, Pacific Gas & Electric (PG&E)