Quick findGo anywhere.

Press ↵ to search · Esc to close

California / Local permit guide

Madera Solar Permit Guide

Your local requirements. The official sources. A clearer next step.

Permit authority
City of Madera Building DivisionSource linked
Electric utility
Pacific Gas and Electric Company (PG&E)Source linked
Local pathway
SolarAPP+ (residential, roof-mounted PV, main dwelling rooftops only)Project-specific eligibility conditions apply.
Review time
1–2 daysSee source scope and conditions below.
See your permit path

Madera County · Explore related utility guides

Source healthLast verified 2026-08-057 official sources5 of 6 core facts verified
Jump to a section
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with City of Madera Building Division and PG&E before making a decision.

Research coverage

Your permit path,
at a glance.

This shows what GridPermit has verified for Madera. It does not show the status of a specific project.

  1. 01Permit authorityCity of Madera Building DivisionAuthority sourced
  2. 02DocumentsChecklist includes conditional itemsConditions apply
  3. 03InspectionInspection guidance for MaderaSteps sourced
  4. 04Utility & PTOPacific Gas and Electric Company (PG&E)Utility path sourced

01 / Know your path

Two approvals.
One project.

Local authority

Permit & inspection

City of Madera Building Division

Local requirements
Electric utility

Interconnection & PTO

Pacific Gas and Electric Company (PG&E)

Utility requirements

A local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.

How to read this guide

GridPermit collects California residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Permit timeline

1–2 days

Inspection requests received before 4:00pm are scheduled for the next workday; requests received after 4:00pm are scheduled 2 days later.

Sources & confidence

Confidence: High (0.8)

Source(s): Automated Residential Solar Permits

Battery/solar incentive program on record

California SGIP - current category and budget check required

New applications and waitlist applications for ratepayer-funded SGIP budgets closed on December 30, 2025. New AB 209 applications have a June 30, 2028 deadline. The 2026 SGIP rate table publishes $3.10/W for solar and $1.10/Wh for storage in applicable Residential Solar and Storage Equity categories. Household eligibility and live budget availability vary by category and program administrator; check the official Program Metrics tracker before relying on an incentive.

Status on file: unknown. Verify current status before relying on this.

Sources & confidence

Confidence: High (0.9)

Source(s): SGIP - Statewide Announcements / About, 2026 Self-Generation Incentive Program Handbook, SGIP Program Metrics and Incentive Step Tracker

02 / Prepare your application

What you need.

0 of 2 markedSaved only on this device; not confirmation of permit readiness.

Sources & confidence

Confidence: High (0.9)

Source(s): Automated Residential Solar Permits

Permit fees

The page states SolarAPP+ charges a processing fee and City fees follow the Master Fee Schedule, but no specific dollar amounts are given.

Not yet verified.

Rebates on record

Rebates on record

Not yet verified.

Utility and generation supplier

Utility

Pacific Gas and Electric Company (PG&E)

Madera is confirmed as within PG&E's electric service territory.

Sources & confidence

Confidence: High (0.85)

Source(s): PG&E's Electric Service Territory

Generation supplier

Not yet verified.

Interconnection

https://www.pge.com/en/about/doing-business-with-pge/interconnections/net-energy-metering-program.html

PG&E's own Net Energy Metering (NEM) program page — a utility-wide fact already established for other PG&E-territory records in this dataset.

Confidence: Medium (0.6)

Permit authority

City of Madera Building Division

Sources & confidence

Confidence: High (0.9)

Source(s): Automated Residential Solar Permits

Permit page: https://www.madera.gov/business-building-development/solar-power/automated-residential-solar-permits/

Inspection steps

  • The field inspector compares the installation to the printed Inspection Checklist on-site
  • Call (559) 661-5445 with the permit number, address, inspection type, and preferred date/time
  • AM slots run 8:00am-12:00pm; PM slots run 1:00pm-4:00pm
  • Reinspection fees apply if the site is unready or revisions are incomplete
Sources & confidence

Confidence: High (0.9)

Source(s): Automated Residential Solar Permits

Eligibility constraints

  • Property types: residential
  • Max system size (AC): Not yet verified.
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: SolarAPP+ (residential, roof-mounted PV, main dwelling rooftops only)
  • Other conditions:
    • Only licensed contractors may use SolarAPP+; owner-builders must use standard permitting
    • Ground-mounted installations, systems exceeding SolarAPP+ size parameters, and non-standard configurations requiring traditional plan review are ineligible for this pathway
Sources & confidence

Confidence: High (0.85)

Source(s): Automated Residential Solar Permits

Official contacts

Official contacts

Confidence: High (0.9)

Need a solar installer who handles permits in Madera?

EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.

Compare quotes from solar installers →

You'll continue on EnergySage's website. GridPermit links to EnergySage as an independent third-party resource. This link is not currently tracked for compensation.

Official sources

Official sources

Frequently Asked Questions

What utility serves solar customers in Madera, California?

Pacific Gas and Electric Company (PG&E) is the interconnection and distribution utility for Madera.

How long does a residential solar permit take in Madera?

Inspection requests received before 4:00pm are scheduled for the next workday; requests received after 4:00pm are scheduled 2 days later.

What documents are required for a solar permit in Madera?

Commonly required documents include: SolarAPP+ Approval Document and Inspection Checklist (generated upon approval); System specifications printouts and City permit documentation, maintained on-site.

Who do I contact about solar permits in Madera?

City of Madera Building Division (Front Counter), phone (559) 661-5440.