Woodside Solar Permit Guide

Pacific Gas & Electric (PG&E) territory · San Mateo County

✓ Last verified 2026-08-097 official sources
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with Town of Woodside Building Department and PG&E before making a decision.

Overview

GridPermit collects California residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Battery/solar incentive program on record

California SGIP - current category and budget check required

New applications and waitlist applications for ratepayer-funded SGIP budgets closed on December 30, 2025. New AB 209 applications have a June 30, 2028 deadline. The 2026 SGIP rate table publishes $3.10/W for solar and $1.10/Wh for storage in applicable Residential Solar and Storage Equity categories. Household eligibility and live budget availability vary by category and program administrator; check the official Program Metrics tracker before relying on an incentive.

Status on file: unknown. Verify current status before relying on this.

Confidence: High (0.9)

Source(s): About, 2026 Self-Generation Incentive Program Handbook, SGIP Program Metrics and Incentive Step Tracker

Permit fees

Not yet verified.

Rebates

Not yet verified.

Utility and generation supplier

Utility

Pacific Gas & Electric (PG&E)

Confidence: High (0.9)

Source(s): Solar Photovoltaic (PV) Systems & Energy Storage Systems (ESS)

Generation supplier

WestLight Energy (formerly Peninsula Clean Energy) (Community Choice Aggregator)

WestLight Energy's own site confirms it is San Mateo County's CCA, formed in 2015 after every city council in the county voted to establish it, serving the entire county (all cities/towns, including Woodside) since 2017. PG&E continues to deliver the power and provide billing/customer service.

Confidence: High (0.8)

Source(s): In the Community

Interconnection

https://www.pge.com/en/save-energy-and-money/rebates-and-incentives/nem.html

PG&E's own utility-wide Net Energy Metering (NEM) program page.

Confidence: Medium (0.55)

Permit authority

Required documents

  • Completed permit application form (required when: always)
  • Eligibility checklist (required when: always)
  • Submittal requirements documentation (required when: always)
  • Plans (minimum 11x17, legible 10-point font) (required when: always)

Confidence: High (0.85)

Source(s): Solar Photovoltaic (PV) Systems & Energy Storage Systems (ESS)

Inspection steps

  • Schedule inspections by calling the Building Department at 650-851-6790 or emailing projectmanagers@woodsideca.gov, at least 72 hours in advance
  • Provide the property address, permit number, and inspection type when scheduling
  • All reviewing departments listed on the permit card (e.g. Building, Planning, Geology, Engineering, Fire District) must finalize before a Building Department Final can be scheduled

This is the Town's general post-permit-issuance inspection process (the same document covers all building permit types, including solar); the Town's page does not describe a separate, solar-specific inspection sequence.

Confidence: Medium (0.65)

Source(s): After a Permit Is Issued

Eligibility constraints

  • Property types: residential
  • Max system size (AC): 10 kW
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: Expedited review for roof-mounted Solar PV (10kW and under) and solar hot water heating
  • Other conditions:
    • Systems exceeding 10kW require different (non-expedited) submittal procedures
    • Class 'A' roofs are required in Woodside, which is in the Wild Land-Urban Interface
    • Fees must be received by the Town before review begins; credit cards are not accepted

Confidence: High (0.85)

Source(s): Solar Photovoltaic (PV) Systems & Energy Storage Systems (ESS)

Official contacts

Confidence: High (0.9)

Need a solar installer who handles permits in Woodside?

EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.

Compare quotes from solar installers →

You'll continue on EnergySage's website. GridPermit has a partner relationship with EnergySage; this link is not currently tracked, and whether the partnership results in compensation to GridPermit has not yet been confirmed.

Sources

Frequently Asked Questions

What utility serves solar customers in Woodside, California?

Pacific Gas & Electric (PG&E) is the interconnection and distribution utility for Woodside. The default electricity generation supplier is WestLight Energy (formerly Peninsula Clean Energy), a Community Choice Aggregator (CCA), separate from Pacific Gas & Electric (PG&E).

What documents are required for a solar permit in Woodside?

Commonly required documents include: Completed permit application form; Eligibility checklist; Submittal requirements documentation; Plans (minimum 11x17, legible 10-point font).

Who do I contact about solar permits in Woodside?

Town of Woodside Building Department, phone 650-851-6790, email projectmanagers@woodsideca.gov.