Electric utility
Colorado Springs Utilities (CSU)Source linked
Local pathway
CSU Solar Energy Program (Connecting Solar) interconnection applicationProject-specific eligibility conditions apply.
See your permit path

El Paso County ·

Source healthLast verified 2026-08-133 official sources4 of 6 core facts verified
Jump to a section
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with Pikes Peak Regional Building Department (PPRBD) and CSU before making a decision.

Research coverage

Your permit path,
at a glance.

This shows what GridPermit has verified for Colorado Springs. It does not show the status of a specific project.

  1. 01Permit authorityPikes Peak Regional Building Department (PPRBD)Authority sourced
  2. 02DocumentsNo complete checklist on fileNot verified
  3. 03InspectionInspection guidance for Colorado SpringsSteps sourced
  4. 04Utility & PTOColorado Springs Utilities (CSU)Utility path sourced

01 / Know your path

Two approvals.
One project.

Local authority

Permit & inspection

Pikes Peak Regional Building Department (PPRBD)

Local requirements
Electric utility

Interconnection & PTO

Colorado Springs Utilities (CSU)

Utility requirements

A local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.

How to read this guide

GridPermit collects Colorado residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Battery/solar incentive program on record

No battery/storage incentive program is on record for this locality.

02 / Prepare your application

What you need.

Not yet verified.

Permit fees

  • Colorado Springs Utilities Solar Energy Program application fee (residential): $100 (flat fee, one-time)

    Per CSU's own 2024 rate case, charged on the customer's next electric bill after their solar installer submits the application. Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

  • Colorado Springs Utilities Solar Energy Program application fee (150 kW or larger systems): $1000 (flat fee, one-time)

    Per CSU's own 2024 rate case; applies to large/commercial-scale systems, not typical residential installations.

Sources & confidence

Confidence: High (0.85)

Source(s): Solar energy (Connecting Solar)

Rebates on record

Rebates on record

Colorado Residential Solar Property Tax Exemption

Statewide Colorado property tax exemption: independently owned residential solar electric generation facilities (photovoltaic systems) meeting the criteria in §39-1-102(6.8), C.R.S. are exempt from Colorado property taxation under §39-3-102, C.R.S. To qualify, the facility must be located on residential real property, used to produce electricity primarily for use in the residential improvements, and have a production capacity of no more than 100 kW AC. This is a genuine statewide exemption applicable to any qualifying Colorado residential system, not utility- or city-specific.

Status on file: active. Verify current status before relying on this.

Sources & confidence

Confidence: High (0.9)

Source(s): Renewable and Clean Energy Assessment (Residential Renewable Energy property tax exemption)

Utility and generation supplier

Utility

Colorado Springs Utilities (CSU)

Colorado Springs operates its own municipal, four-service utility (electric, gas, water, wastewater) — directly confirmed via CSU's own site. This is NOT Xcel Energy territory, unlike Denver.

Sources & confidence

Confidence: High (0.9)

Source(s): Solar energy (Connecting Solar)

Generation supplier

Colorado Springs Utilities (CSU) (utility)

CSU is a municipal utility; no separate Community Choice Aggregator applies. Net metering: monthly net usage is tracked as 'Energy Sent to Grid' minus 'Energy Provided by Grid'; a positive year-end banked credit balance is paid out on the January bill at the current cogeneration rate, approximately $0.02 per kWh (this is the default behavior for a new solar system or a home purchased with an existing system). Customers may instead opt into a one-time, irrevocable 'rollover' election to carry banked credits forward into the next year instead of being paid out. CSU's own site separately states that in 2026 it 'is exploring options to update how residential solar customers interact with our grid' — an active, unresolved policy review at the time of this research, not yet a finalized change, so no altered terms are recorded here beyond what is currently in effect.

Sources & confidence

Confidence: Medium (0.6)

Source(s): Solar energy (Connecting Solar)

Interconnection

https://www.csu.org/solar-energy-program

Confidence: High (0.85)

Permit authority

Pikes Peak Regional Building Department (PPRBD)

NOT a City of Colorado Springs department. PPRBD is a joint regional authority created by a 1966 Inter-Governmental Agreement between El Paso County and the City of Colorado Springs, directly confirmed on both El Paso County's own site and Colorado Springs Utilities' own solar-process page ('it's the installer's responsibility to obtain the proper permits from PPRBD, which verifies codes and laws. PPRBD inspects and closes permits.'). PPRBD is also the building-permit authority for Fountain, Manitou Springs, Calhan, Green Mountain Falls, Monument, Palmer Lake, and (in neighboring Teller County) Woodland Park — the same permit_authority fact is expected to apply to those jurisdictions too, though each would need its own record with its own utility/county verified before publishing.

Sources & confidence

Confidence: High (0.9)

Source(s): Solar energy (Connecting Solar), Pikes Peak Regional Building Department

Permit page: https://www.elpasoco.com/pikes-peak-regional-building-department/

Inspection steps

  • Installer submits a solar interconnection application to Colorado Springs Utilities (CSU) online; CSU reviews it for standards/safety compliance
  • Once CSU approves, it emails approval and system details to the customer, the installer, and PPRBD
  • The installer is then responsible for obtaining the proper permits from PPRBD, which verifies codes and laws
  • PPRBD inspects the installation and closes the permits
  • After all permits are completed, CSU installs an upgraded net meter and a separate production meter, then issues a Permission to Operate (PTO)

Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Sources & confidence

Confidence: High (0.8)

Source(s): Solar energy (Connecting Solar)

Eligibility constraints

  • Property types: residential
  • Max system size (AC): Not yet verified.
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: CSU Solar Energy Program (Connecting Solar) interconnection application
  • Other conditions:
    • Residential application fee tier ($100) applies for systems under 150 kW; a separate commercial/large-system tier ($1,000 fee) applies at 150 kW or larger, per CSU's own page
    • Installer must submit the application on the customer's behalf via CSU's online Connecting Solar portal
    • System must pass CSU's standards/safety review before approval; if denied, required updates are provided to the customer and installer
    • PPRBD permits must be obtained and closed before CSU will install the upgraded net meter and issue a Permission to Operate (PTO)
Sources & confidence

Confidence: High (0.85)

Source(s): Solar energy (Connecting Solar)

Official contacts

Official contacts

Confidence: High (0.8)

Need a solar installer who handles permits in Colorado Springs?

EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.

Compare quotes from solar installers →

You'll continue on EnergySage's website. GridPermit links to EnergySage as an independent third-party resource. This link is not currently tracked for compensation.

Official sources

Official sources

Frequently Asked Questions

What utility serves solar customers in Colorado Springs, Colorado?

Colorado Springs Utilities (CSU) is the interconnection and distribution utility for Colorado Springs. The same utility is also listed as the default electricity generation supplier.

Who do I contact about solar permits in Colorado Springs?

Pikes Peak Regional Building Department, phone 719-327-2880.