Hawaii / Local permit guide

Kahului Solar Permit Guide

Your local requirements. The official sources. A clearer next step.

Electric utility
Maui Electric Company (MECO)Source linked
Local pathway
DSA 18.0 Roof-Mounted PV ProcedureProject-specific eligibility conditions apply.
Review time
Up to 30 daysOnly the stated upper bound is verified. The source's project scope and conditions apply.See source scope and conditions below.
See your permit path

County of Maui ·

Source healthLast verified 2026-08-135 official sources4 of 6 core facts verified
Jump to a section
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with County of Maui Department of Public Works, Development Services Administration (Electrical Permit and Inspection Section) and MECO before making a decision.

Research coverage

Your permit path,
at a glance.

This shows what GridPermit has verified for Kahului. It does not show the status of a specific project.

  1. 01Permit authorityCounty of Maui Department of Public Works, Development Services Administration (Electrical Permit and Inspection Section)Authority sourced
  2. 02DocumentsChecklist includes conditional itemsConditions apply
  3. 03InspectionCurrent inspection sequence needs confirmationNot verified
  4. 04Utility & PTOMaui Electric Company (MECO)Utility path sourced

01 / Know your path

Two approvals.
One project.

Local authority

Permit & inspection

County of Maui Department of Public Works, Development Services Administration (Electrical Permit and Inspection Section)

Local requirements
Electric utility

Interconnection & PTO

Maui Electric Company (MECO)

Utility requirements

A local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.

How to read this guide

GridPermit collects Hawaii residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Permit timeline

Up to 30 days

Only the stated upper bound is verified. The source's project scope and conditions apply.

Per the County's own Electrical Permit and Inspection Section page: 'The electrical permit will be issued within 30 days after the application is deemed complete.'

Sources & confidence

Confidence: High (0.9)

Source(s): Electrical Permit and Inspection Section

Battery/solar incentive program on record

No battery/storage incentive program is on record for this locality.

02 / Prepare your application

What you need.

0 of 4 markedSaved only on this device; not confirmation of permit readiness.

Sources & confidence

Confidence: High (0.95)

Source(s): DSA 18.0 — Permit Requirements for Photovoltaic Systems, Wind Turbines and Windmills

Permit fees

Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Not yet verified.

Rebates on record

Rebates on record

Renewable Energy Technologies Income Tax Credit (RETITC) — Solar Energy System

Statewide Hawaii state income tax credit for solar energy systems (HRS 235-12.5): 35% of actual installed cost, capped at $5,000 per system for single-family residential property (lower of the two), $350 per unit for multi-family residential, or $500,000 per system for commercial property. A separate, higher-value $2,250 cap applies if the system's primary purpose is solar water heating rather than PV. Any utility rebate received must be deducted from system cost before computing the credit. Applies statewide to any Hawaii taxpayer regardless of county/island — a genuine reusable statewide fact, not utility- or county-specific.

Status on file: active. Verify current status before relying on this.

Sources & confidence

Confidence: High (0.9)

Source(s): HRS §235-12.5 — Renewable energy technologies; income tax credit

Utility and generation supplier

Utility

Maui Electric Company (MECO)

Confirmed via the Hawaii Public Utilities Commission's own page and Hawaiian Electric's corporate site; MECO is a Hawaiian Electric Industries subsidiary serving Maui, Lanai, and Molokai under its own tariff, distinct from HECO (Oahu) and HELCO (Hawaii Island). Also directly named on Maui County's own Electrical Permit page ('Maui Electric Company's Engineering Office').

Sources & confidence

Confidence: High (0.9)

Source(s): Smart Renewable Energy Programs, Energy — Electric Utilities Regulated by the Hawaii PUC

Generation supplier

Maui Electric Company (MECO) (utility)

Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Sources & confidence

Confidence: Medium (0.6)

Source(s): Smart Renewable Energy Programs

Permit authority

County of Maui Department of Public Works, Development Services Administration (Electrical Permit and Inspection Section)

Sources & confidence

Confidence: High (0.95)

Source(s): Electrical Permit and Inspection Section, DSA 18.0 — Permit Requirements for Photovoltaic Systems, Wind Turbines and Windmills

Permit page: https://www.mauicounty.gov/1219/Electrical-Permit-and-Inspection-Section

Inspection steps

Not yet verified.

Eligibility constraints

  • Property types: residential, commercial
  • Max system size (AC): Not yet verified.
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: DSA 18.0 Roof-Mounted PV Procedure
  • Other conditions:
    • Roof-mounted PV: an electrical permit is always required; a BUILDING permit is required ONLY IF the licensed architect/structural engineer determines the existing roof truss system cannot support the added weight without additional structural reinforcing — otherwise no building permit is needed for the PV system itself
    • A C-13 licensed electrical contractor is required to obtain the electrical permit; the electrical contractor is responsible for PV system design and installation
    • Free-standing (ground-mounted) PV systems always require BOTH a building permit and an electrical permit, with scaled/detailed site, foundation, elevation, framing, and mounting plans
    • PV systems rated 30 kW or more require schematics prepared, stamped, and signed by a Hawaii-licensed electrical engineer (not just an architect/structural engineer letter)
    • PV systems are allowed on buildings exempt from a building permit under Maui County Code 16.26.106.2 exemptions 1 and 16, but are NOT allowed on structures that were illegally constructed without a required building permit
    • Electrical permits expire if the initial required inspection is not approved within 1 year of issuance; once the initial inspection is approved, the permit remains active up to 5 years from issuance or until final inspection, whichever occurs first
    • Permits for photovoltaic systems may require a separate Fire Permit from the Fire Prevention Bureau
Sources & confidence

Confidence: High (0.95)

Source(s): Electrical Permit and Inspection Section, DSA 18.0 — Permit Requirements for Photovoltaic Systems, Wind Turbines and Windmills

Official contacts

Official contacts
  • County of Maui Electrical Permit and Inspection Section, phone: 808-270-7255, official website
  • Maui Electric Company's Engineering Office, phone: 808-871-2390, official website

Confidence: High (0.9)

Need a solar installer who handles permits in Kahului?

EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.

Compare quotes from solar installers →

You'll continue on EnergySage's website. GridPermit links to EnergySage as an independent third-party resource. This link is not currently tracked for compensation.

Official sources

Official sources

Frequently Asked Questions

What utility serves solar customers in Kahului, Hawaii?

Maui Electric Company (MECO) is the interconnection and distribution utility for Kahului. The same utility is also listed as the default electricity generation supplier.

How long does a residential solar permit take in Kahului?

Per the County's own Electrical Permit and Inspection Section page: 'The electrical permit will be issued within 30 days after the application is deemed complete.' Only the stated upper bound is verified. The source's project scope and conditions apply.

What documents are required for a solar permit in Kahului?

Commonly required documents include: Letter and related forms from a Hawaii-licensed architect or structural engineer verifying the roof assembly (including module mounting system) is structurally adequate; Schematic diagrams showing PV system connections, equipment locations, configuration, and ratings; Schematic diagrams prepared, stamped, and signed by a Hawaii-licensed electrical engineer; Building permit plans (site plan, foundation plan, elevations, framing plans, structural details, module mounting details) stamped by a Hawaii-licensed architect or structural engineer.

Who do I contact about solar permits in Kahului?

County of Maui Electrical Permit and Inspection Section, phone 808-270-7255.