Quick findGo anywhere.

Press ↵ to search · Esc to close

Louisiana / Local permit guide

Baton Rouge Solar Permit Guide

Your local requirements. The official sources. A clearer next step.

Electric utility
Entergy LouisianaSource linked
Local pathway
Not yet verified.
Review time
7 daysSee source scope and conditions below.
See your permit path

East Baton Rouge Parish ·

Source healthLast verified 2026-08-143 official sources5 of 6 core facts verified
Jump to a section
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with City of Baton Rouge / East Baton Rouge Parish, Department of Public Works Permit & Inspection Division and Entergy Louisiana before making a decision.

Research coverage

Your permit path,
at a glance.

This shows what GridPermit has verified for Baton Rouge. It does not show the status of a specific project.

  1. 01Permit authorityCity of Baton Rouge / East Baton Rouge Parish, Department of Public Works Permit & Inspection DivisionAuthority sourced
  2. 02DocumentsChecklist includes conditional itemsConditions apply
  3. 03InspectionCurrent inspection sequence needs confirmationNot verified
  4. 04Utility & PTOEntergy LouisianaUtility path sourced

01 / Know your path

Two approvals.
One project.

Local authority

Permit & inspection

City of Baton Rouge / East Baton Rouge Parish, Department of Public Works Permit & Inspection Division

Local requirements
Electric utility

Interconnection & PTO

Entergy Louisiana

Utility requirements

A local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.

How to read this guide

GridPermit collects Louisiana residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Permit timeline

7 days

Per the City's own FAQ, verbatim: 'Residential plan reviews will be completed within seven (7) business days after receipt of all required information necessary in order to complete an initial review. Residential resubmittals will be reviewed within three (3) business days after receipt.' An optional Expedited Plan Review Service (via the MyGovernmentOnline portal) completes residential reviews within 3 business days instead (resubmittals within 2 business days) for an additional fee not stated on this page. This is the plan-review timeline specifically, not a full permit-to-inspection-complete timeline.

Sources & confidence

Confidence: High (0.85)

Source(s): FAQs - What is the Expedited Plan Review Service?

Battery/solar incentive program on record

No battery/storage incentive program is on record for this locality.

02 / Prepare your application

What you need.

0 of 8 markedSaved only on this device; not confirmation of permit readiness.

Sources & confidence

Confidence: High (0.95)

Source(s): Solar Permit Information

Permit fees

  • Residential Plan Review Fee: $60 (flat fee)

    Per the City's own information sheet.

  • Residential permit fee: $40 (flat fee)

    Per the City's own information sheet: 'Commercial based on project valuation with a minimum of $60, Residential fee: $40.' Electrical and plumbing (water heating) permits are separate and not included in this figure.

Sources & confidence

Confidence: High (0.95)

Source(s): Solar Permit Information

Rebates on record

Rebates on record

Not yet verified.

Utility and generation supplier

Utility

Entergy Louisiana

Entergy Louisiana is Baton Rouge's well-established dominant electric utility (distinct from Entergy New Orleans, which serves the separate New Orleans market with its own net-metering rules).

Sources & confidence

Confidence: High (0.85)

Source(s): Net metering and distributed generation

Generation supplier

Entergy Louisiana (utility)

Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Sources & confidence

Confidence: Medium (0.55)

Source(s): Net metering and distributed generation

Interconnection

https://www.entergylouisiana.com/net-metering

Per Entergy Louisiana's own page: residential net metering covers systems up to 25kW AC. Systems installed by 2019-12-31 are grandfathered at full retail-rate crediting through 2034-12-31. Systems installed after 2019-12-31 use 'two-channel billing' under Rider Schedule DG: the customer pays full retail rate for all grid electricity purchased, while excess exported energy is credited separately at a fixed rate ($0.0259331/kWh, effective 2025-04-01) rather than at the retail rate — a materially lower-value structure than legacy net metering. Monthly bills cannot drop below the fixed Customer Charge; excess credits carry forward. These rules do not apply to Entergy New Orleans customers, who fall under a separate program.

Confidence: High (0.9)

Permit authority

City of Baton Rouge / East Baton Rouge Parish, Department of Public Works Permit & Inspection Division

Enforcement is local: Baton Rouge/East Baton Rouge Parish's own consolidated DPW Permit & Inspection Division is the AHJ. Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Sources & confidence

Confidence: High (0.95)

Source(s): Solar Permit Information

Permit page: https://www.brla.gov/DocumentCenter/View/1674/Solar-Permit-Requirements

Inspection steps

Not yet verified.

Eligibility constraints

  • Property types: residential
  • Max system size (AC): 25 kW
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: Not yet verified.
  • Other conditions:
    • Electrical and plumbing (water heating) permits are separate from the base solar permit and are additionally required
    • The 25kW AC figure recorded here reflects the statewide Entergy Louisiana residential net-metering cap, not a separate City/Parish permit-eligibility limit
Sources & confidence

Confidence: High (0.8)

Source(s): Solar Permit Information, Net metering and distributed generation

Official contacts

Official contacts
  • DPW Permit & Inspection Division, Plan Review Section, phone: 225-389-3105, official website

Confidence: High (0.9)

Need a solar installer who handles permits in Baton Rouge?

EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.

Compare quotes from solar installers →

You'll continue on EnergySage's website. GridPermit links to EnergySage as an independent third-party resource. This link is not currently tracked for compensation.

Official sources

Official sources

Frequently Asked Questions

What utility serves solar customers in Baton Rouge, Louisiana?

Entergy Louisiana is the interconnection and distribution utility for Baton Rouge. The same utility is also listed as the default electricity generation supplier.

How long does a residential solar permit take in Baton Rouge?

Per the City's own FAQ, verbatim: 'Residential plan reviews will be completed within seven (7) business days after receipt of all required information necessary in order to complete an initial review. Residential resubmittals will be reviewed within three (3) business days after receipt.' An optional Expedited Plan Review Service (via the MyGovernmentOnline portal) completes residential reviews within 3 business days instead (resubmittals within 2 business days) for an additional fee not stated on this page. This is the plan-review timeline specifically, not a full permit-to-inspection-complete timeline.

What documents are required for a solar permit in Baton Rouge?

Commonly required documents include: Completed Plan Review application with the plan review fee; Manufacturer documentation showing the mounting/racking system withstands a 105mph wind load, including bolt size, length, and connection spacing to the roof (existing rafters must have purlin bracing installed if not already present); Frame details with setbacks; Plot plan showing the location of solar panels, disconnect(s), inverter, electric meter(s), and batteries (if used); Electrical plan (riser diagram) showing system wiring/connection to the building's electrical system, including wire size/type, grounding, overcurrent protection rating, and disconnects; Manufacturer specifications for the solar panel and inverter, including ratings and overcurrent protection; Plumbing plan including pipe size/type, exchange tank location, backup water heater, pump, and whether the heat exchanger coil directly contacts potable water; requires separate East Baton Rouge Parish Health Unit approval; Design Supervision Statement.

Who do I contact about solar permits in Baton Rouge?

DPW Permit & Inspection Division, Plan Review Section, phone 225-389-3105.