Michigan / Local permit guide

Lansing Solar Permit Guide

Your local requirements. The official sources. A clearer next step.

Electric utility
Lansing Board of Water & Light (BWL)Source linked
Local pathway
Not yet verified.
See your permit path

Ingham County ·

Source healthLast verified 2026-08-143 official sources4 of 6 core facts verified
Jump to a section
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with City of Lansing Building Safety Office (Economic Development & Planning) and BWL before making a decision.

Research coverage

Your permit path,
at a glance.

This shows what GridPermit has verified for Lansing. It does not show the status of a specific project.

  1. 01Permit authorityCity of Lansing Building Safety Office (Economic Development & Planning)Authority sourced
  2. 02DocumentsChecklist includes conditional itemsConditions apply
  3. 03InspectionInspection guidance for LansingSteps sourced
  4. 04Utility & PTOLansing Board of Water & Light (BWL)Utility path sourced

01 / Know your path

Two approvals.
One project.

Local authority

Permit & inspection

City of Lansing Building Safety Office (Economic Development & Planning)

Local requirements
Electric utility

Interconnection & PTO

Lansing Board of Water & Light (BWL)

Utility requirements

A local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.

How to read this guide

GridPermit collects Michigan residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Battery/solar incentive program on record

No battery/storage incentive program is on record for this locality.

02 / Prepare your application

What you need.

0 of 1 markedSaved only on this device; not confirmation of permit readiness.

Sources & confidence

Confidence: Medium (0.6)

Source(s): Building Safety

Permit fees

BWL's own page confirms an interconnection fee applies to the utility application but does not state the dollar amount on the page fetched — left null rather than estimated. Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Not yet verified.

Rebates on record

Rebates on record

BWL Solar Rebate

Rebate for customer-owned residential solar systems. Required documentation: signed rebate application, invoice/proof of purchase, installation date, and equipment specification sheets; processing takes up to 4 weeks.

Status on file: active. Verify current status before relying on this.

Sources & confidence

Confidence: High (0.9)

Source(s): Install My Own Solar

Utility and generation supplier

Utility

Lansing Board of Water & Light (BWL)

Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Sources & confidence

Confidence: High (0.9)

Source(s): Install My Own Solar

Generation supplier

Lansing Board of Water & Light (BWL) (utility)

BWL is a municipally-owned utility that is itself the generation and distribution utility for Lansing; no separate generation supplier or CCA applies.

Sources & confidence

Confidence: High (0.85)

Source(s): Install My Own Solar

Interconnection

https://www.lbwl.com/customers/save-money-energy/install-my-own-solar

Per BWL's own page, customers must contact BWL's distributed generation team before purchasing equipment. BWL compensates excess exported solar energy at a 'Solar Outflow Credit' of $0.075/kWh, itself composed of an energy cost average ($0.050/kWh), a capacity credit ($0.012/kWh), and a renewable energy credit ($0.013/kWh) — a distinct rate-design approach from DTE's Rider 18 program. Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Confidence: High (0.95)

Permit authority

City of Lansing Building Safety Office (Economic Development & Planning)

Michigan's statewide Residential Code sets the baseline, but enforcement is delegated to whichever local jurisdiction has assumed local-enforcing-agency status (see the identical statewide structural note on the Ann Arbor, MI record, mi-washtenaw-annarbor-dte). Lansing's own Building Safety Office is the local AHJ; applications are processed through the City's BS&A Online portal. Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Sources & confidence

Confidence: Medium (0.75)

Source(s): Building Safety

Permit page: https://www.lansingmi.gov/building-safety

Inspection steps

  • Applicant contacts BWL with a request for information; BWL provides the 'Generator Interconnection Application'
  • BWL receives the Interconnection Application, supporting data, and a $100 interconnection application fee
  • BWL acknowledges receipt within 5 business days
  • BWL reviews the application data and confirms the inverter meets IEEE Std. 1547 requirements
  • If approved, the project design is approved for construction; the customer must also have applied for a City of Lansing electrical permit
  • BWL and the local Electrical Inspector approve the completed installation
  • BWL and the customer execute the Generator Interconnection Agreement and contract for parallel operation, and BWL provides Net Metering program information/application

Per BWL's own 'BWL Interconnection Process' flowchart document, specifically scoped to 'Customer Owned Renewable Energy Generators Inverter-Type Projects 20kW or Less' — i.e. The $100 fee shown here is a BWL utility interconnection fee, not a City of Lansing building-permit fee — see permit_fees for the (unconfirmed) City fee. Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Sources & confidence

Confidence: High (0.85)

Source(s): BWL Interconnection Process (Customer Owned Renewable Energy Generators, Inverter-Type Projects 20kW or Less)

Eligibility constraints

  • Property types: residential
  • Max system size (AC): Not yet verified.
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: Not yet verified.
  • Other conditions:
    • BWL's own page recommends contacting the utility's distributed generation team before purchasing equipment to discuss appropriate system sizing
Sources & confidence

Confidence: Medium (0.5)

Source(s): Install My Own Solar

Official contacts

Official contacts

Confidence: High (0.9)

Need a solar installer who handles permits in Lansing?

EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.

Compare quotes from solar installers →

You'll continue on EnergySage's website. GridPermit links to EnergySage as an independent third-party resource. This link is not currently tracked for compensation.

Official sources

Official sources

Frequently Asked Questions

What utility serves solar customers in Lansing, Michigan?

Lansing Board of Water & Light (BWL) is the interconnection and distribution utility for Lansing. The same utility is also listed as the default electricity generation supplier.

What documents are required for a solar permit in Lansing?

Commonly required documents include: Building Permit Application or Application for Plan Review, plus construction documents and the required fee.

Who do I contact about solar permits in Lansing?

BWL Distributed Generation team, phone 517-702-6076, email distributedgeneration@lbwl.com.