Electric utility
Nashville Electric Service (NES)Source linked
Local pathway
Not yet verified.
Review time
7–30 daysSee source scope and conditions below.
See your permit path

Davidson County ·

Source healthLast verified 2026-08-132 official sources6 of 6 core facts verified
Jump to a section
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with Metropolitan Department of Codes and Building Safety and NES before making a decision.

Research coverage

Your permit path,
at a glance.

This shows what GridPermit has verified for Nashville. It does not show the status of a specific project.

  1. 01Permit authorityMetropolitan Department of Codes and Building SafetyAuthority sourced
  2. 02DocumentsChecklist includes conditional itemsConditions apply
  3. 03InspectionInspection guidance for NashvilleSteps sourced
  4. 04Utility & PTONashville Electric Service (NES)Utility path sourced

01 / Know your path

Two approvals.
One project.

Local authority

Permit & inspection

Metropolitan Department of Codes and Building Safety

Local requirements
Electric utility

Interconnection & PTO

Nashville Electric Service (NES)

Utility requirements

A local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.

How to read this guide

GridPermit collects Tennessee residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Permit timeline

7–30 days

Per the City's own page: residential permits typically receive approval within one week, with a standard target of 30 days for completed applications; commercial projects may require extended review. Permits remain valid for 6 months from issuance; work must commence and progress continuously or the permit becomes invalid.

Sources & confidence

Confidence: High (0.8)

Source(s): Solar Panel Photovoltaic Permits

Battery/solar incentive program on record

No battery/storage incentive program is on record for this locality.

02 / Prepare your application

What you need.

0 of 4 markedSaved only on this device; not confirmation of permit readiness.

Sources & confidence

Confidence: High (0.9)

Source(s): Solar Panel Photovoltaic Permits

Permit fees

  • Electrical Photovoltaic permit: $75 (starting fee, may increase marginally depending on fixture and equipment type)

    Per the City's own page.

Sources & confidence

Confidence: High (0.9)

Source(s): Solar Panel Photovoltaic Permits

Rebates on record

Rebates on record

Not yet verified.

Utility and generation supplier

Utility

Nashville Electric Service (NES)

NES is a municipally-owned utility and a local power company (distributor) for the Tennessee Valley Authority (TVA) — TVA generates and transmits power wholesale, while NES handles local distribution, billing, and customer-facing programs. Confirmed directly by the City's own permit page, which requires separate NES approval alongside the Metro Codes permit.

Sources & confidence

Confidence: High (0.9)

Source(s): Solar Panel Photovoltaic Permits

Generation supplier

Tennessee Valley Authority (TVA) (other)

TVA is the wholesale power generator/transmitter for the entire region; NES is the local distribution utility purchasing from TVA and reselling to Nashville-area customers. Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Sources & confidence

Confidence: Medium (0.7)

Source(s): NESolar Connect and NESolar Savings Guidelines (Effective October 2024)

Interconnection

https://www.nespower.com/-/media/project/nes/common/pdfs/nesolar-savings/nesolar-guidelines---102024.pdf

As a TVA local power company, NES does NOT offer traditional retail-rate net metering. Per NES's own 'NESolar Connect and NESolar Savings Guidelines' (effective October 2024), these two formal power-purchase programs are structured for LARGER systems, not typical single-family rooftop installations: NESolar Connect requires a minimum 200kW nameplate for solar facilities (35MW total program cap), and NESolar Savings covers systems up to 250kW DC with a minimum 50kWh average monthly excess generation (10MW total program cap) — both paid at fixed seasonal per-kWh rates (e.g., NESolar Savings: $0.03069/kWh summer, $0.03197/kWh winter) rather than retail-rate credit. Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Confidence: Medium (0.6)

Permit authority

Metropolitan Department of Codes and Building Safety

Tennessee's statewide code framework applies through the state Fire Marshal's office and local adoption, but enforcement is local. Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Sources & confidence

Confidence: High (0.95)

Source(s): Solar Panel Photovoltaic Permits

Permit page: https://www.nashville.gov/departments/codes/construction-and-permits/trades-permits/solar-panel-photovoltaic-permits

Inspection steps

  • Contractors coordinate inspections through the City's e-permits system at appropriate installation stages
  • The inspection phone line is 615-862-6560
Sources & confidence

Confidence: High (0.85)

Source(s): Solar Panel Photovoltaic Permits

Eligibility constraints

  • Property types: residential
  • Max system size (AC): Not yet verified.
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: Not yet verified.
  • Other conditions:
    • The permit application and the NES interconnection application run in parallel and both must be completed before the system can be energized
    • NES's formal NESolar Connect/Savings power-purchase programs require systems well above typical residential scale (200kW+ minimum for Connect); typical single-family rooftop systems fall outside these specific programs and instead use TVA's Dispersed Power Production Program
Sources & confidence

Confidence: Medium (0.7)

Source(s): Solar Panel Photovoltaic Permits, NESolar Connect and NESolar Savings Guidelines (Effective October 2024)

Official contacts

Official contacts
  • Metropolitan Department of Codes and Building Safety, phone: 615-862-6500, official website
  • Codes inspection line, phone: 615-862-6560

Confidence: High (0.85)

Need a solar installer who handles permits in Nashville?

EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.

Compare quotes from solar installers →

You'll continue on EnergySage's website. GridPermit links to EnergySage as an independent third-party resource. This link is not currently tracked for compensation.

Official sources

Official sources

Frequently Asked Questions

What utility serves solar customers in Nashville, Tennessee?

Nashville Electric Service (NES) is the interconnection and distribution utility for Nashville. The default electricity generation supplier is Tennessee Valley Authority (TVA), a other, separate from Nashville Electric Service (NES).

How long does a residential solar permit take in Nashville?

Per the City's own page: residential permits typically receive approval within one week, with a standard target of 30 days for completed applications; commercial projects may require extended review. Permits remain valid for 6 months from issuance; work must commence and progress continuously or the permit becomes invalid.

What documents are required for a solar permit in Nashville?

Commonly required documents include: Electrical Photovoltaic (PV) System permit application; Structural capacity review by a plans examiner; Site/Roof Plan drawn to scale showing panel layout, setbacks, and walking paths; Contractor licensure verification (licensed by the Tennessee Department of Commerce and Insurance).

Who do I contact about solar permits in Nashville?

Metropolitan Department of Codes and Building Safety, phone 615-862-6500.