Overview

GridPermit collects Utah residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Permit timeline

28–56 days

Search-derived reporting (not the City's own page directly) cited a 4-8 week standard review timeline for residential projects; the City's own Solar PV Systems page states the permit becomes null and void if work is not commenced within 180 days of issuance, or if work is suspended/abandoned for 180 days, but does not itself state a review-turnaround day-count.

Confidence: Low (0.4)

Source(s): Solar PV Systems Packet

Battery/solar incentive program on record

No battery/storage incentive program is on record for this locality.

Permit fees

Not yet verified.

Rebates

Not yet verified.

Utility and generation supplier

Utility

Rocky Mountain Power

Confidence: High (0.9)

Source(s): Rooftop Solar — Utah Rooftop Solar Rates Explained

Generation supplier

Rocky Mountain Power (utility)

No Community Choice Aggregator was found serving Salt Lake City's residential solar customers this session; Rocky Mountain Power is recorded as both the distribution and default generation utility.

Confidence: Medium (0.55)

Source(s): Rooftop Solar — Utah Rooftop Solar Rates Explained

Interconnection

https://commerce.utah.gov/ocs/rooftop-solar/

Utah's rooftop-solar customer classification is governed by a settlement agreement and Utah Public Service Commission order, summarized on the Utah Department of Commerce Office of Consumer Services' own page: customers fall into one of three tiers based on when their complete interconnection application was submitted to Rocky Mountain Power — Net-Metered (NEM) if before 2017-11-15, Transition if 2017-11-15 through 2020-10-30, and Post-Transition/Export Credit if after 2020-10-30 (the tier all new applicants fall under today). The exact current Schedule 137 Export Credit Rate dollar/cents-per-kWh figure was not independently confirmed from a primary Utah PSC tariff filing this session (a specific PSC document URL located via search returned HTTP 404) — left unrecorded rather than using a third-party-reported figure.

Confidence: High (0.85)

Permit authority

Salt Lake City Building Services

Utah has no single statewide residential solar permitting portal — permitting authority sits with the local municipality (inside its boundaries) or the county (in unincorporated areas). Salt Lake City's own Building Services division is the permitting authority within city limits.

Confidence: High (0.95)

Source(s): Solar PV

Permit page: https://www.slc.gov/buildingservices/solar-pv/

Required documents

  • Completed Solar PV Packet / Solar PV Application form (required when: always)
  • Site plan showing major component locations and clearances (required when: always)
  • Electrical diagram showing PV array configuration, wiring system, overcurrent protection, inverter, and disconnects (required when: always)
  • Structural worksheet (required when: for certain roof-mounted and ground-mounted systems)

Confidence: High (0.9)

Source(s): Solar PV Systems Packet

Inspection steps

  • Review covers four separate areas: Building Code (roof compliance, weatherproofing, engineered mounting), Structural (roof framing analysis required for systems exceeding 5 psf), Electrical (component certification and configuration verification), and Fire Safety (access pathways, disconnect placement, weather-resistant labeling)
  • Zoning review also applies, covering setback requirements and historic district considerations

Confidence: High (0.85)

Source(s): Solar PV Systems Packet

Eligibility constraints

  • Property types: residential
  • Max system size (AC): 15 kW
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: Not yet verified.
  • Other conditions:
    • Components must be UL listed and identified for the application
    • Maximum 4 series strings per inverter
    • System total capacity may not exceed 15 kW
    • Inverter output limited to 13,440 watts continuous AC power
    • AC connection point must be on the load side of the service disconnecting means
    • Zoning setback requirement of 6 feet minimum
    • Fire-safety access pathway minimum of 3 feet to the roof ridge

Confidence: High (0.9)

Source(s): Solar PV Systems Packet

Official contacts

Confidence: High (0.85)

Need a solar installer who handles permits in Salt Lake City?

EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.

Compare quotes from solar installers →

You'll continue on EnergySage's website. GridPermit has a partner relationship with EnergySage; this link is not currently tracked, and whether the partnership results in compensation to GridPermit has not yet been confirmed.

Sources

Frequently Asked Questions

What utility serves solar customers in Salt Lake City, Utah?

Rocky Mountain Power is the interconnection and distribution utility for Salt Lake City. The default electricity generation supplier is Rocky Mountain Power, a utility, separate from Rocky Mountain Power.

How long does a residential solar permit take in Salt Lake City?

Search-derived reporting (not the City's own page directly) cited a 4-8 week standard review timeline for residential projects; the City's own Solar PV Systems page states the permit becomes null and void if work is not commenced within 180 days of issuance, or if work is suspended/abandoned for 180 days, but does not itself state a review-turnaround day-count.

What documents are required for a solar permit in Salt Lake City?

Commonly required documents include: Completed Solar PV Packet / Solar PV Application form; Site plan showing major component locations and clearances; Electrical diagram showing PV array configuration, wiring system, overcurrent protection, inverter, and disconnects; Structural worksheet.

Who do I contact about solar permits in Salt Lake City?

Salt Lake City Building Services, phone 801-535-6000.