California / Local permit guide

Pomona Solar Permit Guide

Eligible contractor-led projects can use SolarAPP+ and Energov. SCE interconnection and PTO remain separate.

Permit authority
City of Pomona Building and Safety DivisionSource linked
Electric utility
Southern California Edison (SCE)Source linked
Local pathway
SolarAPP+ / Energov auto-issued permit (SB 379)Project-specific eligibility conditions apply.
Review time
Same-day review for eligible expedited-permit projectsNo verified standard-path permit timeline is available.See source scope and conditions below.
See your permit path

Los Angeles County · Explore related utility guides

Source healthLast verified 2026-08-058 official sources5 of 6 core facts verified
Jump to a section
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with City of Pomona Building and Safety Division and SCE before making a decision.

Planning a new solar project? Jump to the homeowner quote path →

Research coverage

Your permit path,
at a glance.

This shows what GridPermit has verified for Pomona. It does not show the status of a specific project.

Quick answer pilot

What are you planning in Pomona?

Choose a project type for the verified local starting point. The full permit guide remains available below.

New rooftop solar
Start with Pomona's SolarAPP+ eligibility check.

Eligible licensed-contractor projects on a permitted main dwelling rooftop can use SolarAPP+ and Energov for an auto-issued City permit, up to 38.4 kW AC. SCE interconnection and PTO are separate.

Review local eligibility
Solar plus battery
Check both SolarAPP+ eligibility and fire requirements.

Pomona's streamlined scope includes eligible paired storage projects up to 38.4 kW AC. Battery projects are also subject to LA County Fire Department requirements, and SCE approval remains separate.

Review battery conditions
Not sure yet
Separate the City permit from the SCE utility step.

Pomona handles the permit and inspection. SCE handles interconnection and permission to operate. Use the guide below to check the requirements for each approval.

Compare the two approvals

No personal information is requested or stored. Selecting an option is an anonymous guide interaction, not a lead or referral.

  1. 01Permit authorityCity of Pomona Building and Safety DivisionAuthority sourced
  2. 02DocumentsChecklist includes conditional itemsConditions apply
  3. 03InspectionInspection guidance for PomonaSteps sourced
  4. 04Utility & PTOSouthern California Edison (SCE)Utility path sourced

Paid referral disclosure: GridPermit has a paid referral relationship with CompareSolarPrices. If you use this link and later complete a qualifying action, GridPermit may receive compensation.

Want a solar quote after reviewing the permit requirements in Pomona?

Continue to CompareSolarPrices to request a homeowner solar quote for Pomona.

Have a recent electricity bill ready. CompareSolarPrices will ask you to confirm your contact details and receipt of its quote. Submit those details only on its website, not to GridPermit.

You will continue on CompareSolarPrices' website. GridPermit is not the installer.

01 / Know your path

Two approvals.
One project.

Local authority

Permit & inspection

City of Pomona Building and Safety Division

Local requirements
Electric utility

Interconnection & PTO

Southern California Edison (SCE)

Utility requirements

A local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.

How to read this guide

GridPermit collects California residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Permit timeline

Same-day review for eligible expedited-permit projects

No verified standard-path permit timeline is available.

The City's own page states licensed contractors can submit 'Residential roof-mounted photovoltaic designs for automated review through SolarAPP+ and the City's online software (Energov) for an auto-issued permit,' consistent with SB 379's real-time issuance requirement (systems up to 38.4kW AC).

Sources & confidence

Confidence: Medium (0.75)

Source(s): Solar Permit Streamlining

02 / Prepare your application

What you need.

0 of 2 markedSaved only on this device; not confirmation of permit readiness.

Sources & confidence

Confidence: Medium (0.7)

Source(s): Solar Permit Streamlining

Battery/solar incentive program on record

California SGIP - current category and budget check required

New applications and waitlist applications for ratepayer-funded SGIP budgets closed on December 30, 2025. New AB 209 applications have a June 30, 2028 deadline. The 2026 SGIP rate table publishes $3.10/W for solar and $1.10/Wh for storage in applicable Residential Solar and Storage Equity categories. Household eligibility and live budget availability vary by category and program administrator; check the official Program Metrics tracker before relying on an incentive.

Status on file: unknown. Verify current status before relying on this.

Sources & confidence

Confidence: High (0.9)

Source(s): SGIP - Statewide Announcements / About, 2026 Self-Generation Incentive Program Handbook, SGIP Program Metrics and Incentive Step Tracker

Permit fees

Not yet verified.

Rebates on record

Rebates on record

Not yet verified.

Utility and generation supplier

Utility

Southern California Edison (SCE)

SCE's own 'Incorporated Cities and Counties Served by SCE' fact sheet (updated 3/17/2025) explicitly lists 'Pomona' by name among the cities in its service area.

Sources & confidence

Confidence: High (0.9)

Source(s): Incorporated Cities and Counties Served by SCE

Generation supplier

Pomona Choice Energy (Community Choice Aggregator)

Pomona Choice Energy is the City of Pomona's own Community Choice Aggregation (CCA) program (not Clean Power Alliance), confirmed directly via its own official site (pomonachoiceenergy.org): 'a locally-managed, not-for-profit energy provider created by the City of Pomona as an alternative to Southern California Edison.' Began serving residential accounts October 2020. Default plan is 'Pomona Choice'; optional tiers include 'Pomona Choice 100' (100% renewable) and 'Pomona Solar Choice'. SCE continues to handle service start/stop, billing, and outages.

Sources & confidence

Confidence: High (0.85)

Source(s): About | Pomona Choice Energy

Interconnection

https://www.sce.com/clean-energy-efficiency/solar-generating-your-own-power/billing-incentives/net-energy-metering

Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Confidence: Medium (0.6)

Permit authority

City of Pomona Building and Safety Division

Sources & confidence

Confidence: High (0.9)

Source(s): Solar Permit Streamlining

Permit page: https://www.pomonaca.gov/government/departments/development-services/building-and-safety-division/solar-permit-streamlining

Inspection steps

  • Schedule an inspection online through the Civic Self Service Online Permit Portal (see the city's 'How to schedule an Online Inspection' guide)
Sources & confidence

Confidence: Medium (0.6)

Source(s): Solar Permit Streamlining

Eligibility constraints

  • Property types: residential
  • Max system size (AC): 38.4 kW
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: SolarAPP+ / Energov auto-issued permit (SB 379)
  • Other conditions:
    • Main dwelling rooftop, permitted, residential structures only
    • No ballasted systems or building-integrated photovoltaic (BIPV) systems
    • Licensed contractors only
    • Projects with energy storage systems (battery back-up) are additionally subject to LA County Fire Department requirements
Sources & confidence

Confidence: High (0.8)

Source(s): Solar Permit Streamlining

Official contacts

Official contacts

Confidence: Medium (0.75)

Official sources

Official sources

Frequently Asked Questions

What utility serves solar customers in Pomona, California?

Southern California Edison (SCE) is the interconnection and distribution utility for Pomona. The default electricity generation supplier is Pomona Choice Energy, a Community Choice Aggregator (CCA), separate from Southern California Edison (SCE).

How long does an expedited-eligible residential solar permit take in Pomona?

The City's own page states licensed contractors can submit 'Residential roof-mounted photovoltaic designs for automated review through SolarAPP+ and the City's online software (Energov) for an auto-issued permit,' consistent with SB 379's real-time issuance requirement (systems up to 38.4kW AC). No verified standard-path permit timeline is available.

What documents are required for a solar permit in Pomona?

Commonly required documents include: Contractor license information (for SolarAPP+ registration); SolarAPP+ approved documents / permit-job card.

Who do I contact about solar permits in Pomona?

Pomona Choice Energy.