Permit authority
Town of San Anselmo Building & SafetySource linked
Electric utility
Pacific Gas & Electric (PG&E)Source linked
Local pathway
Symbium automated permitting platform (SB 379 compliant)Project-specific eligibility conditions apply.
Review time
1–3 daysSee source scope and conditions below.
See your permit path

Marin County · Explore related utility guides

Source healthLast verified 2026-08-097 official sources4 of 6 core facts verified
Jump to a section
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with Town of San Anselmo Building & Safety and PG&E before making a decision.

Research coverage

Your permit path,
at a glance.

This shows what GridPermit has verified for San Anselmo. It does not show the status of a specific project.

  1. 01Permit authorityTown of San Anselmo Building & SafetyAuthority sourced
  2. 02DocumentsNo complete checklist on fileNot verified
  3. 03InspectionInspection guidance for San AnselmoSteps sourced
  4. 04Utility & PTOPacific Gas & Electric (PG&E)Utility path sourced

01 / Know your path

Two approvals.
One project.

Local authority

Permit & inspection

Town of San Anselmo Building & Safety

Local requirements
Electric utility

Interconnection & PTO

Pacific Gas & Electric (PG&E)

Utility requirements

A local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.

How to read this guide

GridPermit collects California residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Permit timeline

1–3 days

Permit processing takes approximately 1-3 business days, depending on staff availability.

Sources & confidence

Confidence: High (0.8)

Source(s): Symbium Solar Permits

Battery/solar incentive program on record

California SGIP - current category and budget check required

New applications and waitlist applications for ratepayer-funded SGIP budgets closed on December 30, 2025. New AB 209 applications have a June 30, 2028 deadline. The 2026 SGIP rate table publishes $3.10/W for solar and $1.10/Wh for storage in applicable Residential Solar and Storage Equity categories. Household eligibility and live budget availability vary by category and program administrator; check the official Program Metrics tracker before relying on an incentive.

Status on file: unknown. Verify current status before relying on this.

Sources & confidence

Confidence: High (0.9)

Source(s): About, 2026 Self-Generation Incentive Program Handbook, SGIP Program Metrics and Incentive Step Tracker

02 / Prepare your application

What you need.

Not yet verified.

Permit fees

Not yet verified.

Rebates on record

Rebates on record

Not yet verified.

Utility and generation supplier

Utility

Pacific Gas & Electric (PG&E)

San Anselmo is a well-documented Marin County city within PG&E's core Northern California service territory.

Sources & confidence

Confidence: High (0.9)

Source(s): Symbium Solar Permits

Generation supplier

MCE (Marin Clean Energy) (Community Choice Aggregator)

MCE's own service-area page confirms San Anselmo as one of Marin County's member communities. PG&E continues to deliver the power and provide billing/customer service.

Sources & confidence

Confidence: High (0.85)

Source(s): Service Area

Interconnection

https://www.pge.com/en/save-energy-and-money/rebates-and-incentives/nem.html

PG&E's own utility-wide Net Energy Metering (NEM) program page.

Confidence: Medium (0.55)

Permit authority

Town of San Anselmo Building & Safety

Sources & confidence

Confidence: High (0.9)

Source(s): Symbium Solar Permits

Permit page: https://www.sananselmo.gov/1979/Symbium-Solar-Permits

Inspection steps

  • Schedule the inspection online through the eTRAKiT portal once the permit is in Issued status
  • Select a morning (9:00 a.m.-12:30 p.m.) or afternoon (1:00 p.m.-4:00 p.m.) window
  • Have the inspection card and Town-stamped plans available on site, with someone present for the full window
  • Inspection results are typically available in eTrakit the following business day

This is the Town's general Building Inspections process (the same page covers all building permit types, including solar); the Town's page does not describe a separate, solar-specific inspection sequence.

Sources & confidence

Confidence: Medium (0.7)

Source(s): Inspections

Eligibility constraints

  • Property types: residential
  • Max system size (AC): Not yet verified.
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: Symbium automated permitting platform (SB 379 compliant)
  • Other conditions:
    • Three permit categories: PV Only Residential, PV with ESS Residential, ESS Only Residential
    • Contractors must meet PV contractor's license requirements per the CSLB's Solar Smart program
    • Some applications may be disqualified from using the automated system and require standard review
Sources & confidence

Confidence: Medium (0.75)

Source(s): Symbium Solar Permits

Official contacts

Official contacts

Confidence: High (0.85)

Need a solar installer who handles permits in San Anselmo?

EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.

Compare quotes from solar installers →

You'll continue on EnergySage's website. GridPermit links to EnergySage as an independent third-party resource. This link is not currently tracked for compensation.

Official sources

Official sources

Frequently Asked Questions

What utility serves solar customers in San Anselmo, California?

Pacific Gas & Electric (PG&E) is the interconnection and distribution utility for San Anselmo. The default electricity generation supplier is MCE (Marin Clean Energy), a Community Choice Aggregator (CCA), separate from Pacific Gas & Electric (PG&E).

How long does a residential solar permit take in San Anselmo?

Permit processing takes approximately 1-3 business days, depending on staff availability.

Who do I contact about solar permits in San Anselmo?

Town of San Anselmo Permit Services, phone 415-258-4616, email permits@townofsananselmo.org.