California / Local permit guide
Berkeley Solar Permit Guide
Your local requirements. The official sources. A clearer next step.
- Permit authority
- City of Berkeley Permit Service Center (Building & Safety Division)Source linked
- Electric utility
- Pacific Gas and Electric Company (PG&E)Source linked
- Local pathway
- Streamlined solar permitting (Permits Online) / SolarAPP+ real-time permittingProject-specific eligibility conditions apply.
- Review time
- 0–5 daysSee source scope and conditions below.
Alameda County · Explore related utility guides
Jump to a section
Planning a new solar project? See the homeowner quote option →
Research coverage
Your permit path,
at a glance.
This shows what GridPermit has verified for Berkeley. It does not show the status of a specific project.
01 / Know your path
Two approvals.
One project.
Permit & inspection
City of Berkeley Permit Service Center (Building & Safety Division)
Local requirementsA local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.
How to read this guide
GridPermit collects California residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.
Permit timeline
0–5 days
Berkeley's Solar Permits page states 'Projects submitted under the standard permit process will be reviewed within one working day.' The Building & Safety Division's submittal-requirements document separately states 'Allow 5 working days for review of plans with calculations' — i.e. specifically when stamped structural engineering calculations are required (non-flush-mounted panels, or roof framing exceeding standard span/spacing limits). No specific timeline is stated for SolarAPP+ real-time or Permits Online streamlined applications.
Sources & confidence
Battery/solar incentive program on record
California SGIP - current category and budget check required
New applications and waitlist applications for ratepayer-funded SGIP budgets closed on December 30, 2025. New AB 209 applications have a June 30, 2028 deadline. The 2026 SGIP rate table publishes $3.10/W for solar and $1.10/Wh for storage in applicable Residential Solar and Storage Equity categories. Household eligibility and live budget availability vary by category and program administrator; check the official Program Metrics tracker before relying on an incentive.
Status on file: unknown. Verify current status before relying on this.
Sources & confidence
02 / Prepare your application
What you need.
Sources & confidence
Permit fees
Berkeley's Solar Permits page states only that the city 'encourages the installation' through 'minimal permit fees,' without a specific dollar figure — not detailed enough to record as a verified fee.
Not yet verified.
Rebates on record
Rebates on record
Not yet verified.
Utility and generation supplier
Utility
Pacific Gas and Electric Company (PG&E)
Ava Community Energy's own Berkeley page confirms PG&E's continued role as the underlying transmission/distribution/billing utility, stating the Renewable 100 default product 'costs an additional 1¾ cent per kilowatt-hour above PG&E rates' and that customers may 'return to PG&E service.' Ava is a separate default generation supplier layered on top of PG&E delivery — see generation_supplier.
Sources & confidence
Generation supplier
Ava Community Energy - Renewable 100 (default for most residential customers) / Bright Choice (automatic for CARE, FERA, and Medical Baseline customers) (Community Choice Aggregator)
Per Ava Community Energy's own Berkeley page: 'In June 2021, the Berkeley City Council voted to set the default electricity option for Berkeley residents (except those on CARE, FERA, and/or Medical Baseline rates) to Ava's Renewable 100 service starting in March 2022... residential customers on the CARE, FERA, or Medical Baseline programs automatically remain on Bright Choice.' This is a different default product than the Fremont record's (Bright Choice) — a genuine per-city council decision, not an inconsistency.
Sources & confidence
Interconnection
Same PG&E-wide Net Energy Metering program URL already verified for the Fremont, Oakland, San Jose, Fresno, and Stockton records — reused here as a utility-level fact (PG&E's NEM program page is the same for every city in its distribution territory, not city-specific). Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.
Inspection steps
- Final inspection required after installation and before the solar system is granted final approval
- Inspections may be scheduled through Permits Online, the automated phone scheduling system at (844) 216-2170, or by phone at (510) 981-7440 (option 1)
Sources & confidence
Eligibility constraints
- Property types: single-family, duplex
- Max system size (AC): 10 kW
- Max system size (DC): Not yet verified.
- Max thermal capacity: Not yet verified.
- Program/pathway: Streamlined solar permitting (Permits Online) / SolarAPP+ real-time permitting
- Other conditions:
- Must mark all items 'Yes' on the Eligibility Checklist for Solar Streamlining to use the streamlined process; SolarAPP+ has its own separate eligibility checklist referenced on the same page.
Sources & confidence
Official contacts
Official contacts
- City of Berkeley Permit Service Center, phone: (510) 981-7500, email: permits@berkeleyca.gov, official website
- SGIP Program Administrator (PG&E territory), phone: 415-973-6436, email: selfgen@pge.com, official website
Need a solar installer who handles permits in Berkeley?
EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.
Compare quotes from solar installers →You'll continue on EnergySage's website. GridPermit links to EnergySage as an independent third-party resource. This link is not currently tracked for compensation.
Official sources
Official sources
- Solar Permits | City of Berkeley, City of Berkeley (government). Accessed 2026-08-03.
- Solar Photovoltaic (PV) System Submittal Requirements, City of Berkeley Planning and Development, Building & Safety Division (government). Accessed 2026-08-03.
- Berkeley Electricity Provider | Ava Community Energy, Ava Community Energy (other_official). Accessed 2026-08-03.
- 1.04.010 Definitions | Berkeley Municipal Code, City of Berkeley (hosted by American Legal Publishing) (government). Accessed 2026-08-03.
- Self-Generation Incentive Program (SGIP), California Public Utilities Commission (cpuc). Accessed 2026-08-01.
- SGIP - Statewide Announcements / About, Self-Generation Incentive Program (statewide administrator site) (program_administrator). Accessed 2026-08-01.
- Net Energy Metering (NEM) Program | PG&E, Pacific Gas and Electric Company (utility). Accessed 2026-08-01.
- SGIP - Contact, Self-Generation Incentive Program (statewide administrator site) (program_administrator). Accessed 2026-08-01.
- 2026 Self-Generation Incentive Program Handbook, Self-Generation Incentive Program Program Administrators (program_administrator). Accessed 2026-08-26.
- SGIP Program Metrics and Incentive Step Tracker, Self-Generation Incentive Program Program Administrators (program_administrator). Accessed 2026-08-26.
Frequently Asked Questions
What utility serves solar customers in Berkeley, California?
Pacific Gas and Electric Company (PG&E) is the interconnection and distribution utility for Berkeley. The default electricity generation supplier is Ava Community Energy - Renewable 100 (default for most residential customers) / Bright Choice (automatic for CARE, FERA, and Medical Baseline customers), a Community Choice Aggregator (CCA), separate from Pacific Gas and Electric Company (PG&E).
How long does a residential solar permit take in Berkeley?
Berkeley's Solar Permits page states 'Projects submitted under the standard permit process will be reviewed within one working day.' The Building & Safety Division's submittal-requirements document separately states 'Allow 5 working days for review of plans with calculations' — i.e. specifically when stamped structural engineering calculations are required (non-flush-mounted panels, or roof framing exceeding standard span/spacing limits). No specific timeline is stated for SolarAPP+ real-time or Permits Online streamlined applications.
What documents are required for a solar permit in Berkeley?
Commonly required documents include: Cover Sheet (project address, owner and preparer contact info, scope of work, unit count, sheet index, legend); Schematic Site Plan (property lines, PV system location, main electrical panel/subpanels, equipment and disconnect locations); Permit Application (Building, Electrical, Mechanical, Plumbing); Electrical Plan (single line diagram of PV and utility interconnect, conductor/raceway specifications); Roof Plan and Cross-Section (roof layout, module attachment, fire-safety access pathways and labeling); Manufacturer's Specification Sheets (make, model, listing, size, weight for inverters, panels, racks, combiner boxes).
Who do I contact about solar permits in Berkeley?
City of Berkeley Permit Service Center, phone (510) 981-7500, email permits@berkeleyca.gov.
Related cities
Related cities
Other verified cities related to Berkeley. See all cities on the California solar permit guide index.