California / Local permit guide

Campbell Solar Permit Guide

Your local requirements. The official sources. A clearer next step.

Electric utility
Pacific Gas & Electric (PG&E)Source linked
Local pathway
Automatic (SolarApp+) or non-automatic Renewable Energy permitProject-specific eligibility conditions apply.
Review time
1–10 daysSee source scope and conditions below.
See your permit path

Santa Clara County · Explore related utility guides

Source healthLast verified 2026-08-096 official sources4 of 6 core facts verified
Jump to a section
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with City of Campbell Building Inspection Division and PG&E before making a decision.

Research coverage

Your permit path,
at a glance.

This shows what GridPermit has verified for Campbell. It does not show the status of a specific project.

  1. 01Permit authorityCity of Campbell Building Inspection DivisionAuthority sourced
  2. 02DocumentsNo complete checklist on fileNot verified
  3. 03InspectionCurrent inspection sequence needs confirmationNot verified
  4. 04Utility & PTOPacific Gas & Electric (PG&E)Utility path sourced

01 / Know your path

Two approvals.
One project.

Local authority

Permit & inspection

City of Campbell Building Inspection Division

Local requirements
Electric utility

Interconnection & PTO

Pacific Gas & Electric (PG&E)

Utility requirements

A local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.

How to read this guide

GridPermit collects California residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Permit timeline

1–10 days

Automatic Renewable Energy permit applications are issued upon payment (1 day); non-automatic Renewable Energy permit applications are reviewed in-house and take 5-10 days.

Sources & confidence

Confidence: High (0.8)

Source(s): Simple Construction Part II Application Guide — Renewable Energy Systems (SolarApp)

Battery/solar incentive program on record

California SGIP - current category and budget check required

New applications and waitlist applications for ratepayer-funded SGIP budgets closed on December 30, 2025. New AB 209 applications have a June 30, 2028 deadline. The 2026 SGIP rate table publishes $3.10/W for solar and $1.10/Wh for storage in applicable Residential Solar and Storage Equity categories. Household eligibility and live budget availability vary by category and program administrator; check the official Program Metrics tracker before relying on an incentive.

Status on file: unknown. Verify current status before relying on this.

Sources & confidence

Confidence: High (0.9)

Source(s): About, 2026 Self-Generation Incentive Program Handbook, SGIP Program Metrics and Incentive Step Tracker

02 / Prepare your application

What you need.

Not yet verified.

Permit fees

  • Non-automatic Renewable Energy permit partial refund: $196 (flat)

    Automatic Renewable Energy permits are non-refundable; non-automatic permits are partially refundable at this amount.

Sources & confidence

Confidence: Medium (0.6)

Source(s): Simple Construction Part II Application Guide — Renewable Energy Systems (SolarApp)

Rebates on record

Rebates on record

Not yet verified.

Utility and generation supplier

Utility

Pacific Gas & Electric (PG&E)

Campbell is a well-documented Santa Clara County city within PG&E's core Northern California service territory.

Sources & confidence

Confidence: High (0.9)

Source(s): Simple Construction Part II Application Guide — Renewable Energy Systems (SolarApp)

Generation supplier

Silicon Valley Clean Energy (SVCE) (Community Choice Aggregator)

SVCE's own 'The Agency' page confirms Campbell as one of 13 member jurisdictions. PG&E continues to deliver the power and provide billing/customer service.

Sources & confidence

Confidence: High (0.85)

Source(s): The Agency

Interconnection

https://www.pge.com/en/save-energy-and-money/rebates-and-incentives/nem.html

PG&E's own utility-wide Net Energy Metering (NEM) program page.

Confidence: Medium (0.55)

Permit authority

City of Campbell Building Inspection Division

Sources & confidence

Confidence: High (0.85)

Source(s): Simple Construction Part II Application Guide — Renewable Energy Systems (SolarApp)

Permit page: https://www.campbellca.gov/1458/Building-Inspection-Division-Home

Inspection steps

Not yet verified.

Eligibility constraints

  • Property types: residential
  • Max system size (AC): Not yet verified.
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: Automatic (SolarApp+) or non-automatic Renewable Energy permit
  • Other conditions:
    • Renewable Energy permits may only be issued to contractors holding a B General, C-10 Electrical, C-46 Solar, or C-39 Roofing California license, or an owner-builder doing the work themselves
    • An issued Renewable Energy permit expires 365 days from issuance
Sources & confidence

Confidence: High (0.8)

Source(s): Simple Construction Part II Application Guide — Renewable Energy Systems (SolarApp)

Official contacts

Official contacts

Confidence: High (0.85)

Need a solar installer who handles permits in Campbell?

EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.

Compare quotes from solar installers →

You'll continue on EnergySage's website. GridPermit links to EnergySage as an independent third-party resource. This link is not currently tracked for compensation.

Official sources

Official sources

Frequently Asked Questions

What utility serves solar customers in Campbell, California?

Pacific Gas & Electric (PG&E) is the interconnection and distribution utility for Campbell. The default electricity generation supplier is Silicon Valley Clean Energy (SVCE), a Community Choice Aggregator (CCA), separate from Pacific Gas & Electric (PG&E).

How long does a residential solar permit take in Campbell?

Automatic Renewable Energy permit applications are issued upon payment (1 day); non-automatic Renewable Energy permit applications are reviewed in-house and take 5-10 days.

Who do I contact about solar permits in Campbell?

City of Campbell Building Inspection Division, phone 408-866-2130, email building@campbellca.gov.