Permit authority
City of Highland Building & SafetySource linked
Electric utility
Southern California Edison (SCE)Source linked
Local pathway
SolarAPP+ (fastest option) / standard permitting (all other systems)Project-specific eligibility conditions apply.
Review time
1–3 daysSee source scope and conditions below.
See your permit path

San Bernardino County · Explore related utility guides

Source healthLast verified 2026-08-087 official sources5 of 6 core facts verified
Jump to a section
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with City of Highland Building & Safety and SCE before making a decision.

Research coverage

Your permit path,
at a glance.

This shows what GridPermit has verified for Highland. It does not show the status of a specific project.

  1. 01Permit authorityCity of Highland Building & SafetyAuthority sourced
  2. 02DocumentsChecklist includes conditional itemsConditions apply
  3. 03InspectionInspection guidance for HighlandSteps sourced
  4. 04Utility & PTOSouthern California Edison (SCE)Utility path sourced

Paid referral disclosure: GridPermit has a paid referral relationship with CompareSolarPrices. If you use this link and later complete a qualifying action, GridPermit may receive compensation.

Want a solar quote after reviewing the permit requirements in Highland?

Continue to CompareSolarPrices to request a homeowner solar quote for Highland.

Have a recent electricity bill ready. CompareSolarPrices will ask you to confirm your contact details and receipt of its quote. Submit those details only on its website, not to GridPermit.

You will continue on CompareSolarPrices' website. GridPermit is not the installer.

01 / Know your path

Two approvals.
One project.

Local authority

Permit & inspection

City of Highland Building & Safety

Local requirements
Electric utility

Interconnection & PTO

Southern California Edison (SCE)

Utility requirements

A local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.

How to read this guide

GridPermit collects California residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Permit timeline

1–3 days

Electronic portal submittals are typically reviewed within 1-3 business days (most same-day); standard in-person review is expedited to 1-2 days. SolarAPP+ provides instant approval eligibility determination.

Sources & confidence

Confidence: Medium (0.75)

Source(s): Photovoltaic Energy Systems (SOLAR)

Battery/solar incentive program on record

California SGIP - current category and budget check required

New applications and waitlist applications for ratepayer-funded SGIP budgets closed on December 30, 2025. New AB 209 applications have a June 30, 2028 deadline. The 2026 SGIP rate table publishes $3.10/W for solar and $1.10/Wh for storage in applicable Residential Solar and Storage Equity categories. Household eligibility and live budget availability vary by category and program administrator; check the official Program Metrics tracker before relying on an incentive.

Status on file: unknown. Verify current status before relying on this.

Sources & confidence

Confidence: High (0.9)

Source(s): SGIP - Statewide Announcements / About, 2026 Self-Generation Incentive Program Handbook, SGIP Program Metrics and Incentive Step Tracker

02 / Prepare your application

What you need.

0 of 5 markedSaved only on this device; not confirmation of permit readiness.

Sources & confidence

Confidence: High (0.85)

Source(s): Photovoltaic Energy Systems (SOLAR)

Permit fees

The page states application fees are collected at submittal, and that SolarAPP+ includes a processing fee covering up to three revisions, but does not state specific dollar amounts.

Not yet verified.

Rebates on record

Rebates on record

Not yet verified.

Utility and generation supplier

Utility

Southern California Edison (SCE)

SCE's own 'Incorporated Cities and Counties Served by SCE' fact sheet (updated 3/17/2025) explicitly lists 'Highland' by name among the cities in its service area.

Sources & confidence

Confidence: High (0.9)

Source(s): Incorporated Cities and Counties Served by SCE

Generation supplier

Not yet verified.

Interconnection

https://www.sce.com/clean-energy-efficiency/solar-generating-your-own-power/billing-incentives/net-energy-metering

Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Confidence: Medium (0.6)

Permit authority

City of Highland Building & Safety

Sources & confidence

Confidence: High (0.9)

Source(s): Photovoltaic Energy Systems (SOLAR)

Permit page: https://www.highlandca.gov/357/Photovoltaic-Energy-Systems-SOLAR

Inspection steps

  • Schedule inspection through the city's inspection line
  • Approved plans and job card must remain on-site during construction
  • Final inspection confirms proper installation
Sources & confidence

Confidence: High (0.8)

Source(s): Photovoltaic Energy Systems (SOLAR)

Eligibility constraints

  • Property types: residential
  • Max system size (AC): 38.4 kW
  • Max system size (DC): Not yet verified.
  • Max thermal capacity: Not yet verified.
  • Program/pathway: SolarAPP+ (fastest option) / standard permitting (all other systems)
  • Other conditions:
    • SolarAPP+ pathway limited to rooftop installations on primary dwellings, licensed contractors only, up to 38.4kW AC, excludes ground-mounted or ballasted systems
    • Any ground-mounted system or roof-mounted system on a Historic-designated structure requires Planning Division approval before a building permit can be issued
Sources & confidence

Confidence: High (0.85)

Source(s): Photovoltaic Energy Systems (SOLAR)

Official contacts

Official contacts

Confidence: High (0.85)

Official sources

Official sources

Frequently Asked Questions

What utility serves solar customers in Highland, California?

Southern California Edison (SCE) is the interconnection and distribution utility for Highland.

How long does a residential solar permit take in Highland?

Electronic portal submittals are typically reviewed within 1-3 business days (most same-day); standard in-person review is expedited to 1-2 days. SolarAPP+ provides instant approval eligibility determination.

What documents are required for a solar permit in Highland?

Commonly required documents include: Completed Building Permit Application (in-person); Two sets of plans and two sets of structural calculations (in-person); Signed contractor declarations; Current business license verification; Notarized authorization letter (if a representative signs).

Who do I contact about solar permits in Highland?

City of Highland Building & Safety, phone 909-864-6861.