California / Local permit guide

San Leandro Solar Permit Guide

Your local requirements. The official sources. A clearer next step.

Electric utility
Pacific Gas and Electric Company (PG&E)Source linked
Local pathway
Not yet verified.
Review time
3–7 daysSee source scope and conditions below.
See your permit path

Alameda County · Explore related utility guides

Source healthLast verified 2026-08-038 official sources6 of 6 core facts verified
Jump to a section
Informational only. This page is not legal, engineering, or permit advice. Every fact below links to the official source it came from and shows how confident we are in it. Verify current requirements with City of San Leandro Building & Safety Division and PG&E before making a decision.

Research coverage

Your permit path,
at a glance.

This shows what GridPermit has verified for San Leandro. It does not show the status of a specific project.

  1. 01Permit authorityCity of San Leandro Building & Safety DivisionAuthority sourced
  2. 02DocumentsChecklist includes conditional itemsConditions apply
  3. 03InspectionInspection guidance for San LeandroSteps sourced
  4. 04Utility & PTOPacific Gas and Electric Company (PG&E)Utility path sourced

01 / Know your path

Two approvals.
One project.

Local authority

Permit & inspection

City of San Leandro Building & Safety Division

Local requirements
Electric utility

Interconnection & PTO

Pacific Gas and Electric Company (PG&E)

Utility requirements

A local permit and utility permission to operate are different approvals. Check the local sequence and requirements below.

How to read this guide

GridPermit collects California residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.

Permit timeline

3–7 days

The PV Submittal Guidelines state: 'After you pay the application fee, you will receive a permit number, which will be assigned to Permit Staff within 3 to 5 business days,' then for residential projects 'Initial Plans Review can take 3 to 7 business days before plan check comments or final packaging instructions are given. Resubmittal Reviews can also take another 3 to 7 business days.' The min/max recorded here (3-7 days) represents the Initial Plans Review stage specifically, the closest single figure to a 'permit review timeline'; the full process can take longer if a resubmittal round is needed, and commercial/industrial review windows are longer (12-15 and 10-12 business days) and out of scope for a residential-only record.

Sources & confidence

Confidence: High (0.85)

Source(s): City of San Leandro PV Submittal Guidelines (Updated 2/2026)

Battery/solar incentive program on record

California SGIP - current category and budget check required

New applications and waitlist applications for ratepayer-funded SGIP budgets closed on December 30, 2025. New AB 209 applications have a June 30, 2028 deadline. The 2026 SGIP rate table publishes $3.10/W for solar and $1.10/Wh for storage in applicable Residential Solar and Storage Equity categories. Household eligibility and live budget availability vary by category and program administrator; check the official Program Metrics tracker before relying on an incentive.

Status on file: unknown. Verify current status before relying on this.

Sources & confidence

Confidence: High (0.9)

Source(s): SGIP - Statewide Announcements / About, 2026 Self-Generation Incentive Program Handbook, SGIP Program Metrics and Incentive Step Tracker

02 / Prepare your application

What you need.

0 of 4 markedSaved only on this device; not confirmation of permit readiness.

Sources & confidence

Confidence: High (0.9)

Source(s): City of San Leandro PV Submittal Guidelines (Updated 2/2026)

Permit fees

Confidence reflects a verified fact about fee timing, not a verified dollar amount — no amount is invented.

  • Building/Electrical Permit Fee: amount not verified

    The Submittal Guidelines state: 'Permit Fees are due when the permit is ready to be issued,' i.e. after plan review is complete, before the permit is issued and construction may begin. Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Sources & confidence

Confidence: Medium (0.5)

Source(s): City of San Leandro PV Submittal Guidelines (Updated 2/2026)

Rebates on record

Rebates on record

Not yet verified.

Utility and generation supplier

Utility

Pacific Gas and Electric Company (PG&E)

Ava Community Energy's own San Leandro page confirms PG&E's continued delivery/billing role: San Leandro accounts are 'automatically enrolled in Ava's Renewable 100 service' while remaining PG&E customers for delivery and billing (Ava is a separate default generation supplier layered on top of PG&E — see generation_supplier).

Sources & confidence

Confidence: High (0.85)

Source(s): San Leandro Electricity Provider | Ava Community Energy

Generation supplier

Ava Community Energy - Renewable 100 (default for residential, municipal, and commercial accounts) (Community Choice Aggregator)

Per Ava's own San Leandro page: 'The City of San Leandro helped found Ava in 2016—and has been using Ava's clean energy since 2018. Its residential, municipal, and commercial accounts are automatically enrolled in Ava's Renewable 100 service.'

Sources & confidence

Confidence: High (0.9)

Source(s): San Leandro Electricity Provider | Ava Community Energy

Interconnection

https://www.pge.com/en/about/doing-business-with-pge/interconnections/net-energy-metering-program.html

Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Confidence: Medium (0.6)

Permit authority

City of San Leandro Building & Safety Division

Sources & confidence

Confidence: High (0.9)

Source(s): Solar Permitting Guidelines | San Leandro, CA, City of San Leandro PV Submittal Guidelines (Updated 2/2026)

Permit page: https://www.sanleandro.org/241/Solar-Permitting-Guidelines

Inspection steps

  • Construction can begin only after the permit is issued
  • The project is considered complete when the Final Inspection result is Pass

Some supporting official material could not be independently confirmed from the full source in GridPermit's latest review. Verify the current requirement with the authority before relying on it.

Sources & confidence

Confidence: Medium (0.7)

Source(s): City of San Leandro PV Submittal Guidelines (Updated 2/2026)

Eligibility constraints

Not yet verified.

Official contacts

Official contacts

Confidence: High (0.85)

Need a solar installer who handles permits in San Leandro?

EnergySage is an independent solar marketplace where you can request property-specific pricing from installers familiar with local permitting.

Compare quotes from solar installers →

You'll continue on EnergySage's website. GridPermit links to EnergySage as an independent third-party resource. This link is not currently tracked for compensation.

Official sources

Official sources

Frequently Asked Questions

What utility serves solar customers in San Leandro, California?

Pacific Gas and Electric Company (PG&E) is the interconnection and distribution utility for San Leandro. The default electricity generation supplier is Ava Community Energy - Renewable 100 (default for residential, municipal, and commercial accounts), a Community Choice Aggregator (CCA), separate from Pacific Gas and Electric Company (PG&E).

How long does a residential solar permit take in San Leandro?

The PV Submittal Guidelines state: 'After you pay the application fee, you will receive a permit number, which will be assigned to Permit Staff within 3 to 5 business days,' then for residential projects 'Initial Plans Review can take 3 to 7 business days before plan check comments or final packaging instructions are given. Resubmittal Reviews can also take another 3 to 7 business days.' The min/max recorded here (3-7 days) represents the Initial Plans Review stage specifically, the closest single figure to a 'permit review timeline'; the full process can take longer if a resubmittal round is needed, and commercial/industrial review windows are longer (12-15 and 10-12 business days) and out of scope for a residential-only record.

What documents are required for a solar permit in San Leandro?

Commonly required documents include: Plans (site plan; roof framing plan and cross-section; elevation/section detail; attachment detail and load calculations; grounding detail; single line diagram) combined into one PDF, stamped/signed if prepared by an architect or engineer; Photo of the existing Main Electric Service Panel with the dead front off showing the breakers; Labels, including one with contact information for the qualified maintenance and service provider (per 2025 CRC R330.11 #2); Manufacturer Specifications for the solar panel, inverter, attachment system, and energy storage systems.

Who do I contact about solar permits in San Leandro?

City of San Leandro Building & Safety Division, phone (510) 577-3405, email PermitsByEmail@SanLeandro.org.