Torrance Solar Permit Guide
Southern California Edison (SCE) territory · Los Angeles County
Overview
GridPermit collects California residential solar and permitting facts directly from official sources (city, county, and state government sites, utilities, and public utilities commissions) and shows only what we can verify, with a confidence score and a link to where it came from. Nothing here is estimated or inferred beyond what's stated below. See our methodology for the rules this page follows.
Battery/solar incentive program on record
California SGIP - current category and budget check required
New applications and waitlist applications for ratepayer-funded SGIP budgets closed on December 30, 2025. New AB 209 applications have a June 30, 2028 deadline. The 2026 SGIP rate table publishes $3.10/W for solar and $1.10/Wh for storage in applicable Residential Solar and Storage Equity categories. Household eligibility and live budget availability vary by category and program administrator; check the official Program Metrics tracker before relying on an incentive.
Status on file: unknown. Verify current status before relying on this.
Permit fees
Not yet verified.
Rebates
Not yet verified.
Utility and generation supplier
Utility
Southern California Edison (SCE)
Generation supplier
Southern California Edison (SCE) (utility)
Clean Power Alliance's own homepage states it serves '38 communities across Los Angeles and Ventura counties' and names each one individually via its site's community directory; Torrance is not among the named communities. No other Los Angeles/Ventura County CCA serving Torrance was found, so Southern California Edison (SCE) is recorded as both the distribution and generation utility.
Interconnection
SCE's own Net Energy Metering (NEM) program page — a utility-wide fact already established for other SCE-territory records this session.
Required documents
- Roof layout (required when: always)
- Line diagram (required when: always)
- Equipment data sheets (required when: always)
Inspection steps
- Call the 24/7 Interactive Voice Response (IVR) Voice Permits Line at (310) 618-5901 to schedule or cancel an inspection
- Have the Record (Permit) Number and a three-digit Inspection Code ready before calling
- Cancellations must be requested before 6:00 AM the day of the inspection
- A confirmation number is issued at the end of the call for reference
This is the City's general Building & Safety inspection-scheduling process (covers Building and Electrical permit types, including solar); the City does not publish a separate, solar-specific inspection sequence.
Eligibility constraints
- Property types: residential
- Max system size (AC): 38.4 kW
- Max system size (DC): Not yet verified.
- Max thermal capacity: Not yet verified.
- Program/pathway: Automated Solar Permitting (Citizen Access Portal)
- Other conditions:
- New PV system on an existing, permitted R-3 (residential) occupancy only; no existing PV or ESS already on the property
- Ground-mounted systems, carports, and non-permanent structures are not allowed; flush-mount or non-hillside tilt-mount only
- No trenching, structural modifications, or alterations to the structure allowed
- Individual ESS max 20kWh, aggregate ESS max 80kWh, sited per California Fire Code setback/location rules
- Projects not meeting the automated-permitting criteria may still submit for standard plan review via the online portal
Official contacts
- SGIP Program Administrator (SCE territory), email: SGIPGroup@sce.com, official website
Paid referral disclosure: GridPermit has a paid referral relationship with CompareSolarPrices. If you use this link and later complete a qualifying action, GridPermit may receive compensation.
Want a solar quote after reviewing the permit requirements in Torrance?
Continue to CompareSolarPrices to request a homeowner solar quote for Torrance.
You will continue on CompareSolarPrices' website. GridPermit is not the installer.
Sources
- Solar / Photovoltaic, City of Torrance (government). Accessed 2026-08-11.
- Incorporated Cities and Counties Served by SCE, Southern California Edison (utility). Accessed 2026-08-06.
- Net Energy Metering (NEM) Time of Use, Southern California Edison (utility). Accessed 2026-08-03.
- SGIP - Statewide Announcements / About, Self-Generation Incentive Program (statewide administrator site) (program_administrator). Accessed 2026-08-01.
- SGIP - Contact, Self-Generation Incentive Program (statewide administrator site) (program_administrator). Accessed 2026-08-01.
- Homepage (community directory listing all 38 CPA member communities), Clean Power Alliance (other_official). Accessed 2026-08-10.
- Torrance PV Automated Permitting Requirements, City of Torrance (government). Accessed 2026-08-11.
- Schedule Building Inspection, City of Torrance (government). Accessed 2026-08-11.
- 2026 Self-Generation Incentive Program Handbook, Self-Generation Incentive Program Program Administrators (program_administrator). Accessed 2026-08-26.
- SGIP Program Metrics and Incentive Step Tracker, Self-Generation Incentive Program Program Administrators (program_administrator). Accessed 2026-08-26.
Frequently Asked Questions
What utility serves solar customers in Torrance, California?
Southern California Edison (SCE) is the interconnection and distribution utility for Torrance. The default electricity generation supplier is Southern California Edison (SCE), a utility, separate from Southern California Edison (SCE).
What documents are required for a solar permit in Torrance?
Commonly required documents include: Roof layout; Line diagram; Equipment data sheets.
Who do I contact about solar permits in Torrance?
SGIP Program Administrator (SCE territory), email SGIPGroup@sce.com.
Related California cities
Other verified cities related to Torrance. See all cities on the California solar permit guide index.
- Alhambra, Southern California Edison (SCE)
- Arcadia, Southern California Edison (SCE)
- Azusa, Azusa Light & Water
- Baldwin Park, Southern California Edison (SCE)
- Beverly Hills, Southern California Edison (SCE)
- Burbank, Burbank Water and Power (BWP)